A project manager is creating a report of the final status of a closed project to the stakeholders. Which of the following is NOT used in a final project report to communicate the status of a project? A. Variance information B. Lessons learned C. Scope baseline D. Status of deliverables You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. Which of the following is the BEST metric to use for forecasting? A. ETC and VAC B. EV and AC C. SV and CV D. SPI and CPI Information about the project must be distributed to all stakeholders. Which of the following process outputs is used to report the status and cost of project activities? A. Issue logs B. Work performance information C. Status reports D. Project records
A project manager is creating a report of the final status of a closed project to
the stakeholders. Which of the following is NOT used in a final project report
to communicate the status of a project?
A. Variance information
B. Lessons learned
C. Scope baseline
D. Status of deliverables
You are the project manager for a railroad construction project. Your sponsor
has asked you for a forecast for the cost of project completion. Which of the
following is the BEST metric to use for
A. ETC and VAC
B. EV and AC
C. SV and CV
D. SPI and CPI
Information about the project must be distributed to all stakeholders. Which
of the following process outputs is used to report the status and cost of
project activities?
A. Issue logs
B. Work performance information
C. Status reports
D. Project records