A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 7 units/hr 5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding Assembly 2.1 units/hr 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) V is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places).
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 7 units/hr 5 units/hr Assembly 0.8 units/hr Sawing Sanding Welding Assembly 2.1 units/hr 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) V is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places).
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:### Production Process Flowchart at Kenneth Day Manufacturing
The flowchart illustrates a production process with multiple stages at Kenneth Day Manufacturing. The process consists of several operations with different production rates, where:
- **Sawing**: 7 units per hour.
- **Sanding**: 5 units per hour.
- **Drilling**: 2.5 units per hour.
- **Welding**: 2.1 units per hour.
- **Assembly (three parallel lines)**: Each line operates at 0.8 units per hour.
The drilling operation occurs separately but simultaneously with the sawing and sanding, which are consecutive operations. A product is required to pass through only one of the three parallel assembly operations.
#### Questions:
a) Identify the bottleneck operation.
b) Calculate the bottleneck time in minutes per unit (rounded to two decimal places).
c) Determine the throughput time of the overall system in minutes (rounded to two decimal places).
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.