a) Produce  work schedule showing the activity of estimated durations and the critical path and estimated overal mean duration for work package. Answers must be handwritten step by step to allow others to follow. b) calculate the probability of the work package being completed by week 24. Answers must be handwritten step by step to allow others to follow. c) Differentiate between ealiest and latest activity start and finisg times and explain how these variables determine the degree of spare time or float  contained within activities.  Answers must be handwritten step by step to allow others to follow.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

a) Produce  work schedule showing the activity of estimated durations and the critical path and estimated overal mean duration for work package. Answers must be handwritten step by step to allow others to follow.

b) calculate the probability of the work package being completed by week 24. Answers must be handwritten step by step to allow others to follow.

c) Differentiate between ealiest and latest activity start and finisg times and explain how these variables determine the degree of spare time or float  contained within activities.  Answers must be handwritten step by step to allow others to follow.

QUESTION FOUR (4)
Refer to Table 3 This table shows your estimates of optimistic, likely and pessimistic
durations for activities to be carried in one of the work packages.
Table 3: Estimated activity times for works to be completed by company
Optimistic duration
Likely duration
(weeks)
1
(weeks)
2
Activity
XA-B
B-C
C-D
C-E
C-F
D-H
E-G
AF-G
F-1
F
AG-H
XH44
AHS
XJ-K
3
2
3
2
3
NW
2
-
2
22
2
2
+
3
32
2
5
3
Pessimistic duration
(weeks)
3
3
3
3
5
5
3
6
4
5
10
5
63
Transcribed Image Text:QUESTION FOUR (4) Refer to Table 3 This table shows your estimates of optimistic, likely and pessimistic durations for activities to be carried in one of the work packages. Table 3: Estimated activity times for works to be completed by company Optimistic duration Likely duration (weeks) 1 (weeks) 2 Activity XA-B B-C C-D C-E C-F D-H E-G AF-G F-1 F AG-H XH44 AHS XJ-K 3 2 3 2 3 NW 2 - 2 22 2 2 + 3 32 2 5 3 Pessimistic duration (weeks) 3 3 3 3 5 5 3 6 4 5 10 5 63
Expert Solution
steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.