A process (Process #440) is under study to be controlled using control limits and X and R charts. A process that is expected to have a measured mean of 15 units has been sampled 20 times, using 5 samples each time for a total of 100 samples. The values that were measured are given below. In addition, for your convenience, the mean (X) and range (R) of each set of samples is also provided. Samples from process to be controlled Range Sample Number Sample Values Mean (x) (R) 1 18.65 21.45 21.45 22.25 22.65 21.29 14.00 20.65 2 20.85 22.05 22.05 22.45 21.61 1.80 20.65 20.65 21.45 22.25 22.25 21.45 1.60 18.85 19.25 20.65 21.05 21.05 20.17 2.20 20.45 21.25 22.05 22.05 22.25 21.61 1.80 19.45 20.05 20.45 21.25 22.65 20.77 3.20 19.05 20.25 20.85 21.45 22.25 20.77 3.20 18.85 19.05 19.45 19.65 21.65 19.73 2.80 9 19.25 19.45 20.25 20.45 21.25 20.13 2.00 10 18.85 19.05 21.45 21.85 22.25 20.69 3.40 11 19.45 20.25 20.85 21.05 22.05 20.73 2.60 12 19.25 19.45 20.25 22.05 22.25 20.65 3.00 13 18.65 19.65 21.25 21.25 22.25 20.61 3.60 14 18.65 18.85 21.25 22.65 22.65 20.81 14.00 15 18.65 18.85 19.45 20.65 21.45 19.81 2.80 16 19.05 20.85 121.45 22.05 22.65 21.21 3.60 17 23.65 25.05 25.05 25.45 27.45 25.33 3.80 18 18.85 18.85 19.25 20.45 22.25 19.93 3.40 19 19.45 19.85 20.25 21.05 22.45 13.00 120.61 20 21.05 21.25 21.25 22.45 22.45 21.69 1.40 Using the above table of samples the preliminary UCL is calculated as The preliminary LCLR is calculated as 0. After discarding any points that fall outside the control limits the final UCL is calculated as the final LCLR is calculated as 0, and the R control chart mean is calculated as and the preliminary LCL is calculated as We now need to calculate the X charts control limits. The preliminary UCL is calculated as After discarding any outlying samples, and repeating until no samples are outside the limits, the final mean is with a final UCLX of and a final LCL of 3 4 5 6 7 18

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
A process (Process #440) is under study to be controlled using control limits and X and R charts.
A process that is expected to have a measured mean of 15 units has been sampled 20 times, using 5 samples each time for a total of 100 samples. The values that were measured are given below. In addition, for your convenience, the mean (X) and range
(R) of each set of samples is also provided.
Samples from process to be controlled
Mean
Range
Sample Number
Sample Values
(X)
(R)
11
18.66
21.45
21.45
22.26
22.65
21.29
4.00
20.65
20.85
22.05
22.05
22.45
21.61
1.80
20.65
20.65
21.45
22.25
22.25
21.45
1.60
18.85
19.25
20.65
21.05
21.05
20.17
2.20
20.45
21.25
22.05
22.05
22.25
21.61
1.80
19.45
20.05
20.45
21.25
22.65
20.77
3.20
19.05
20.25
20.85
21.45
22.25
20.77
3.20
18.85
19.05
19.45
19.65
21.65
19.73
2.80
19.25
19.45
20.25
20.45
21.25
20.13
2.00
10
18.86
19.05
21.45
21.85
22.26
20.69
3.40
11
19.45
20.25
20.85
21.05
22.05
20.73
2.60
12
19.25
19.45
20.25
22.06
22.25
20.65
3.00
13
18.65
19.65
21.25
21.25
22.25
20.61
3.60
14
18.65
18.685
21.25
22.65
22.65
20.81
4.00
15
18.65
18.85
19.45
20.65
21.45
19.81
2.80
16
19.05
20.85
21.45
22.05
22.65
21.21
3.60
17
23.65
25.05
25.05
25.45
27.45
125.33
3.80
18
18.85
18.85
19.25
20.45
22.25
19.93
3.40
19
19.45
19.85
121.05
22.45
120.61
3.00
20.25
21.25
20
21.05
21.25
22.45
22.45
21.69
1.40
Using the above table of samples the preliminary UCLA is calculated as
The preliminary LCLR is calculated as 0.
After discarding any points that fall outside the control limits the final UCLA is calculated as
, the final LCLR is calculated as 0, and the R control chart mean is calculated as
and the preliminary LCLX is calculated as
We now need to calculate the X charts control limits. The preliminary UCLX is calculated as
After discarding any outlying samples, and repeating until no samples are outside the limits, the final mean is
with a final UCLX of
and a final LCLX of
2
13
4
5
6
7
8
19
Transcribed Image Text:A process (Process #440) is under study to be controlled using control limits and X and R charts. A process that is expected to have a measured mean of 15 units has been sampled 20 times, using 5 samples each time for a total of 100 samples. The values that were measured are given below. In addition, for your convenience, the mean (X) and range (R) of each set of samples is also provided. Samples from process to be controlled Mean Range Sample Number Sample Values (X) (R) 11 18.66 21.45 21.45 22.26 22.65 21.29 4.00 20.65 20.85 22.05 22.05 22.45 21.61 1.80 20.65 20.65 21.45 22.25 22.25 21.45 1.60 18.85 19.25 20.65 21.05 21.05 20.17 2.20 20.45 21.25 22.05 22.05 22.25 21.61 1.80 19.45 20.05 20.45 21.25 22.65 20.77 3.20 19.05 20.25 20.85 21.45 22.25 20.77 3.20 18.85 19.05 19.45 19.65 21.65 19.73 2.80 19.25 19.45 20.25 20.45 21.25 20.13 2.00 10 18.86 19.05 21.45 21.85 22.26 20.69 3.40 11 19.45 20.25 20.85 21.05 22.05 20.73 2.60 12 19.25 19.45 20.25 22.06 22.25 20.65 3.00 13 18.65 19.65 21.25 21.25 22.25 20.61 3.60 14 18.65 18.685 21.25 22.65 22.65 20.81 4.00 15 18.65 18.85 19.45 20.65 21.45 19.81 2.80 16 19.05 20.85 21.45 22.05 22.65 21.21 3.60 17 23.65 25.05 25.05 25.45 27.45 125.33 3.80 18 18.85 18.85 19.25 20.45 22.25 19.93 3.40 19 19.45 19.85 121.05 22.45 120.61 3.00 20.25 21.25 20 21.05 21.25 22.45 22.45 21.69 1.40 Using the above table of samples the preliminary UCLA is calculated as The preliminary LCLR is calculated as 0. After discarding any points that fall outside the control limits the final UCLA is calculated as , the final LCLR is calculated as 0, and the R control chart mean is calculated as and the preliminary LCLX is calculated as We now need to calculate the X charts control limits. The preliminary UCLX is calculated as After discarding any outlying samples, and repeating until no samples are outside the limits, the final mean is with a final UCLX of and a final LCLX of 2 13 4 5 6 7 8 19
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman