A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $360,000 and direct labor hours would be 45,000. Actual factory overhead costs incurred were $377,200, and actual direct labor hours were 47,000. What is the amount of overapplied or underapplied manufacturing overhead at the end of the year?
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
A manufacturing company applies factory
beginning of the year, it estimated that
direct labor hours would be 45,000. Actual factory overhead costs incurred were
$377,200, and actual direct labor hours were 47,000. What is the amount of
overapplied or underapplied manufacturing overhead at the end of the year?