A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. ID Description Predecessor Time (days) A Survey None 11 B Soils report A 26 C Traffic design A 23 D Lot layout A 10 E Approve design B, C, D 85 F Illumination E 20 G S Drainage E 28 H Landscape E 21 I Signage E 25 ] Bid proposal F, G, H, I 8 The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity in days. A, B, E, G, J dauley

Information Technology Project Management
9th Edition
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter6: Project Schedule Management
Section: Chapter Questions
Problem 1E
icon
Related questions
Question
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.
ID
Description
Predecessor
Time
(days)
A
Survey
None
11
B
Soils report
A
26
C
Traffic design
A
23
D
Lot layout
A
10
E
Approve design
B, C, D
85
F
Illumination
E
20
G
S
Drainage
E
28
H
Landscape
E
21
I
Signage
E
25
] Bid proposal
F, G, H, I
8
The project is expected to take
The critical path is:
Early start for Activity E is:
Late finish for Activity F is:
Slack for Activity in
days.
A, B, E, G, J
dauley
Transcribed Image Text:A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. ID Description Predecessor Time (days) A Survey None 11 B Soils report A 26 C Traffic design A 23 D Lot layout A 10 E Approve design B, C, D 85 F Illumination E 20 G S Drainage E 28 H Landscape E 21 I Signage E 25 ] Bid proposal F, G, H, I 8 The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity in days. A, B, E, G, J dauley
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning
Enhanced Discovering Computers 2017 (Shelly Cashm…
Enhanced Discovering Computers 2017 (Shelly Cashm…
Computer Science
ISBN:
9781305657458
Author:
Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:
Cengage Learning
Principles of Information Systems (MindTap Course…
Principles of Information Systems (MindTap Course…
Computer Science
ISBN:
9781285867168
Author:
Ralph Stair, George Reynolds
Publisher:
Cengage Learning