A large electronics manufacturer is considering outsourcing the manufacturing of a diaphragm used in its large speaker. The company estimates that annual fixed costs of manufacturing the part in-house, which include equipment, maintenance, and management, amounts to $6.9 million. The variable costs of labor and material are $7 per unit. The company has an offer from a major subcontractor to produce the part for \$12 per unit. However, the subcontractor wants the company to share in the costs of the equipment. The electronics company estimates that the total cost would be $3.4 million, which also includes management oversight for the new supply contact. The company must consume more than diaphragms to make the manufacturing the part in-house option least costly. (Enter your response rounded up to the nearest whole number.).
A large electronics manufacturer is considering outsourcing the manufacturing of a diaphragm used in its large speaker. The company estimates that annual fixed costs of manufacturing the part in-house, which include equipment, maintenance, and management, amounts to
$6.9
million. The variable costs of labor and material are
$7
per unit. The company has an offer from a major subcontractor to produce the part for \$12 per unit. However, the subcontractor wants the company to share in the costs of the equipment. The electronics company estimates that the total cost would be
$3.4
million, which also includes management oversight for the new supply contact. The company must consume more than diaphragms to make the manufacturing the part in-house option least costly. (Enter your response rounded up to the nearest whole number.).
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images