A contractor needs 214 yd' of aggregate base material for a highway construction project. It will be compacted to a dry unit weight of 130 lb/ft'. This material is available in a stockpile at a local material supply yard, but is sold by the ton, not by the cubic yard. The moisture content of the stockpile is 7.0%. (a) How many tons of aggregate base material should the contractor purchase to have exactly the correct volume of compacted material? (b) The contractor purchased the material per the computation in part (a), and it exactly met the needs at the project site. An intense rainstorm occurred the following week, which delayed further construction and raised the moisture content of the stockpile to 19.0%. Now, the contractor needs to prepare another identical section of aggregate base and is ordering the same number of tons as before. How many cubic yards of compacted aggregate base will be produced from this second shipment? How will it compare with the first shipment? Explain.
A contractor needs 214 yd' of aggregate base material for a highway construction project. It will be compacted to a dry unit weight of 130 lb/ft'. This material is available in a stockpile at a local material supply yard, but is sold by the ton, not by the cubic yard. The moisture content of the stockpile is 7.0%. (a) How many tons of aggregate base material should the contractor purchase to have exactly the correct volume of compacted material? (b) The contractor purchased the material per the computation in part (a), and it exactly met the needs at the project site. An intense rainstorm occurred the following week, which delayed further construction and raised the moisture content of the stockpile to 19.0%. Now, the contractor needs to prepare another identical section of aggregate base and is ordering the same number of tons as before. How many cubic yards of compacted aggregate base will be produced from this second shipment? How will it compare with the first shipment? Explain.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
100%
question attached.
Expert Solution
Step 1
Given
Need of aggregate = 214 yd3
Dry density yd=113 lb/ft3
moisture content = 7%
To find
a)Aggregate required for exact correct volume of compacted material
b)Compacted aggregate in 2nd shipment and comparision with 1st shipment
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning