A contractor has a job which should be completed in 120 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 150 days. Of the 80 men, 50 are each paid Php 150.00 a day, 25 at Php 210.00, and 5 at Php 280.00. For each day beyond the original 120 days, the contractor has to pay Php 1,500.00 liquidated damages. How many more men should the contractor add so that he can complete the work on time?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter9: Pricing Construction Equipment
Section: Chapter Questions
Problem 6RQ
icon
Related questions
Question

A contractor has a job which should be completed in 120 days. At present, he has 80 men on the job and it is estimated that they will finish the work in 150 days. Of the 80 men, 50 are each paid Php 150.00 a day, 25 at Php 210.00, and 5 at Php 280.00. For each day beyond the original 120 days, the contractor has to pay Php 1,500.00 liquidated damages. How many more men should the contractor add so that he can complete the work on time?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Pricing of General Work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,