A contractor enters into a revenue contract to construct customized equipment for a customer. The contract price is $250,000 plus a $125,000 bonus if the customized equipment is completed by a specified date. The contract is expected to take three years to complete. The contractor has extensive experience in building customized equipment. The award fee is paid only if the customized equipment is completed by the agreed upon date. Otherwise, the contractor receives no bonus. The contractor estimates that it is 85% likely that the contract will be completed successfully and in advance of the target date. Required Determine the transaction price for revenue recognition for the contractor.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

9

A contractor enters into a revenue contract to construct customized equipment for a customer. The
contract price is $250,000 plus a $125,000 bonus if the customized equipment is completed by a
specified date. The contract is expected to take three years to complete. The contractor has extensive
experience in building customized equipment. The award fee is paid only if the customized
equipment is completed by the agreed upon date. Otherwise, the contractor receives no bonus. The
contractor estimates that it is 85% likely that the contract will be completed successfully and in
advance of the target date. Required Determine the transaction price for revenue recognition for the
contractor.
Transcribed Image Text:A contractor enters into a revenue contract to construct customized equipment for a customer. The contract price is $250,000 plus a $125,000 bonus if the customized equipment is completed by a specified date. The contract is expected to take three years to complete. The contractor has extensive experience in building customized equipment. The award fee is paid only if the customized equipment is completed by the agreed upon date. Otherwise, the contractor receives no bonus. The contractor estimates that it is 85% likely that the contract will be completed successfully and in advance of the target date. Required Determine the transaction price for revenue recognition for the contractor.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education