A civil engineer involved in construction management must decide between two ways to pump concrete up to the top floors of a seven-story office building under construction. Plan 1 requires the purchase of equipment for $6000 which costs between $0.40 and $0.75 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The asset is able to pump 100 metric tons per day. If purchased, the asset will last for 5 years, have no salvage value, and be used 50 days per year. Plan 2 is an equipment-leasing option and is expected to cost the company $2500 per year for equipment with a low cost estimate of $1800 and a high estimateof $3200 per year. In addition, an extra $5 per hour labor cost will be incurred for operating the leased equipment each 8-hour day. Use i = 12% per year. (a) Which plan should the engineer recommend on the basis of the most likely estimates of costs? (b) Will the decision above change if the pessimistic estimates are used?

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
Question

A civil engineer involved in construction management must decide between two ways to pump concrete up to the top floors of a seven-story office building under construction. Plan 1 requires the purchase of equipment for $6000 which costs between $0.40 and $0.75 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The asset is able to pump 100 metric tons per day. If purchased, the asset will last for 5 years, have no salvage value, and be used 50 days per year. Plan 2 is an equipment-leasing option and is expected to cost the company $2500 per year for equipment with a low cost estimate of $1800 and a high estimate
of $3200 per year. In addition, an extra $5 per hour labor cost will be incurred for operating the leased equipment each 8-hour day. Use i = 12% per year. (a) Which plan should the engineer recommend on the basis of the most likely estimates of costs? (b) Will the decision above change if the pessimistic estimates are used?

Expert Solution
steps

Step by step

Solved in 4 steps with 8 images

Blurred answer
Knowledge Booster
Accounting for Impairment of Assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education