A bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required is currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $360,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $170,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $170,000 plus an extra $23,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $170,000 + 7x($23,000) = $331,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic estimate Most likely estimate Optimistic estimate End of year 4 End of year 7 End of year 8

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
(a) Calculate the PW of costs for the different scenarios of Alternative 2

PW<sub>pessimistic</sub>(8%) = $ ___ thousand (Round to one decimal place.)

PW<sub>most likely</sub>(8%) = $ ___ thousand (Round to one decimal place.)

PW<sub>optimistic</sub>(8%) = $ ___ thousand (Round to one decimal place.)

(b) Calculate the expected PW costs of Alternative 2 using the "three-point estimation" technique

Expected PW = $ ___ thousand (Round to one decimal place.)

(c) Based on these estimates, which alternative is more economical?

○ A. Alternative 1

○ B. Alternative 2
Transcribed Image Text:(a) Calculate the PW of costs for the different scenarios of Alternative 2 PW<sub>pessimistic</sub>(8%) = $ ___ thousand (Round to one decimal place.) PW<sub>most likely</sub>(8%) = $ ___ thousand (Round to one decimal place.) PW<sub>optimistic</sub>(8%) = $ ___ thousand (Round to one decimal place.) (b) Calculate the expected PW costs of Alternative 2 using the "three-point estimation" technique Expected PW = $ ___ thousand (Round to one decimal place.) (c) Based on these estimates, which alternative is more economical? ○ A. Alternative 1 ○ B. Alternative 2
**Bridge Construction Alternatives**

A bridge is to be constructed as part of a new road. Engineers have determined that the current traffic volume on the new road will justify a two-lane road and a bridge at present. However, due to uncertainties regarding future traffic, the timing of the need for additional lanes is being studied. Two alternatives are under consideration:

**Alternative 1 - One-stage construction:** 
Build a four-lane bridge immediately at a cost of $360,000.

**Alternative 2 - Two-stage construction:** 
Start with a two-lane bridge now for $170,000 and widen it to four lanes when traffic demands. The future cost of widening the bridge to four lanes will be $170,000, plus an extra $23,000 for each year the widening is postponed. For instance, if the widening occurs at the end of year 7, the additional cost will be $331,000, calculated as $170,000 + 7($23,000).

**Estimates for the need to widen to a four-lane bridge:**

- **Pessimistic estimate:** End of year 4
- **Most likely estimate:** End of year 7
- **Optimistic estimate:** End of year 8

This analysis considers the anticipated timing and costs associated with each construction alternative to aid in decision-making.
Transcribed Image Text:**Bridge Construction Alternatives** A bridge is to be constructed as part of a new road. Engineers have determined that the current traffic volume on the new road will justify a two-lane road and a bridge at present. However, due to uncertainties regarding future traffic, the timing of the need for additional lanes is being studied. Two alternatives are under consideration: **Alternative 1 - One-stage construction:** Build a four-lane bridge immediately at a cost of $360,000. **Alternative 2 - Two-stage construction:** Start with a two-lane bridge now for $170,000 and widen it to four lanes when traffic demands. The future cost of widening the bridge to four lanes will be $170,000, plus an extra $23,000 for each year the widening is postponed. For instance, if the widening occurs at the end of year 7, the additional cost will be $331,000, calculated as $170,000 + 7($23,000). **Estimates for the need to widen to a four-lane bridge:** - **Pessimistic estimate:** End of year 4 - **Most likely estimate:** End of year 7 - **Optimistic estimate:** End of year 8 This analysis considers the anticipated timing and costs associated with each construction alternative to aid in decision-making.
Expert Solution
Step 1: Define Present Worth:

The present worth of multiple cash flows is given as the sum of all the present worths of the individual cash flow series. Present worth is a component of the time value of money which provides us with the value of money today.

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Knowledge Booster
Highway Construction
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education