a-1. Determine the critical path. A-B-D-G A-B-E-G A-C-F-G OA-C-E-G a-2. Determine the early completion time in weeks for the project. Early completion time weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 111
A-B-D-G
OA-B-E-G
A-C-F-G
OA-C-E-G
a-2. Determine the early completion time in weeks for the project.
Early completion time
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
NORMAL
TIME
NORMAL CRASH
COST
$ 7,000
5
12,000
5,000
4,000
3,000
6,000
7,000
ACTIVITY
A
B
E
F
G
10
8
6
7
4
4
weeks
TIME CRASH COST
3
Resulting cost to crash
7
7
5
6
3
3
b-1. Which activities in order of reduction would be shortened?
O A-G-D
O G-D-A
OD-G-A
O D-B-C
b-2. Find the resulting cost to crash.
$13,000
18,000
7,000
5,000
6,000
7,000
9,000
Transcribed Image Text:A-B-D-G OA-B-E-G A-C-F-G OA-C-E-G a-2. Determine the early completion time in weeks for the project. Early completion time For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened. NORMAL TIME NORMAL CRASH COST $ 7,000 5 12,000 5,000 4,000 3,000 6,000 7,000 ACTIVITY A B E F G 10 8 6 7 4 4 weeks TIME CRASH COST 3 Resulting cost to crash 7 7 5 6 3 3 b-1. Which activities in order of reduction would be shortened? O A-G-D O G-D-A OD-G-A O D-B-C b-2. Find the resulting cost to crash. $13,000 18,000 7,000 5,000 6,000 7,000 9,000
The following CPM network has estimates of the normal time in weeks listed for the activities:
A(5)
A-B-D-G
A-B-E-G
A-C-F-G
OA-C-E-G
B(10)
a-1. Determine the critical path.
C(8)
Early completion time
D(6)
weeks
E(7)
a-2. Determine the early completion time in weeks for the project.
F(4)
G(4)
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
Transcribed Image Text:The following CPM network has estimates of the normal time in weeks listed for the activities: A(5) A-B-D-G A-B-E-G A-C-F-G OA-C-E-G B(10) a-1. Determine the critical path. C(8) Early completion time D(6) weeks E(7) a-2. Determine the early completion time in weeks for the project. F(4) G(4) For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 7 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.