8. Which of the following statements is NOT TRUE with Extreme Programming? a The key emphases of extreme Programming are its use of two-person programming teams and having a customer on-site during the development process. b. With XP, analysis and design phases of the life cycle link into a series of activities based on the basic processes of coding, testing, listening, and designing. c. In XP, coding and testing are related parts of the same process, which means the programmers who write the code can also develop the tests. d. The overall philosophy of XP is that code will be integrated into the system it is being developed for and tested within a few hours after it has been written. 9. Which of the following is an advantage of rapid application development? a. It allows for the simultaneous gathering and consolidating of large amounts of information. b. Software engineers can start working on the project earlier rather than wading through a lengthy early design process. c. It is useful for projects in which the user requirements are uncertain or not precise. d. Assists in identifying any problems with the efficacy of earlier design, requirements analysis and coding activities. 10. Which of the following is a drawback of spiral model? It does not accept the expected changes and revisions that become necessary with most projects. b. Estimation of budget and time are harder to judge at the beginning of the project since the requirements evolve through the process c. It opens up many scope of interpersonal conflict d. It allows for the simultaneous gathering and consolidating of large amounts of information.

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question
Cin
Paste
H
155
=
Home
Cut
E Copy
✔Format Painter
Clipboard
Insert
Page: 3 of 4 Words: 39
HH
G
Page Layout
Calibri (Body)
BIU
Type here to search
References
- 11
abe X, X Aa
Font
Mailings
Aal
Review
Α Α΄ B-B-S $ENT
Paragraph
8. Which of the following statements is NOT TRUE with Extreme Programming?
a. The key emphases of eXtreme Programming are its use of two-person programming
teams and having a customer on-site during the development process.
b.
With XP, analysis and design phases of the life cycle link into a series of activities based
on the basic processes of coding, testing, listening, and designing.
View
c.
In XP, coding and testing are related parts of the same process, which means the
programmers who write the code can also develop the tests.
d. The overall philosophy of XP is that code will be integrated into the system it is being
developed for and tested within a few hours after it has been written.
9. Which of the following is an advantage of rapid application development?
a. It allows for the simultaneous gathering and consolidating of large amounts of
information.
a. I, II, and III
b. I and II only
c. I and III only
d. II and III only
b. Software engineers can start working on the project earlier rather than wading through a
lengthy early design process.
c. It is useful for projects in which the user requirements are uncertain or not precise.
d. Assists in identifying any problems with the efficacy of earlier design, requirements
analysis and coding activities.
SAD Chapter quiz 1 - Microsoft Word
10. Which of the following is a drawback of spiral model?
a. It does not accept the expected changes and revisions that become necessary with most
projects.
b. Estimation of budget and time are harder to judge at the beginning of the project since
the requirements evolve through the process.
c.
It opens up many scope of inter-personal conflict.
d. It allows for the simultaneous gathering and consolidating of large amounts of
information.
11. Which of the following is NOT a driving force in project initiation?
a. To respond to an opportunity
b. To resolve a problemy
c. To conform to a directive
d. To increase market share
12. Which of the following is a process in developing a cost-benefit analysis?
1. Estimate the anticipated development and operational costs.
II. Estimate the anticipated financial benefits.
II. Estimate of costs and benefits.
O
13. Which of the following is the purpose of technical feasibility?
a. To measure how well the solution will work in the organization and how people feel about
the system/project.
b. For systems analyst to gain understanding of the likelihood that all potential time frames
and completion date schedules can be met and that meeting these dates will be sufficient
for dealing with the needs of the organization.
To gain understanding of the organization's ability to construct the proposed system.
All of the hous
HI
AaBb CcDc AaBb CcDc Aa Bbc AaBb AaBb CCD AaB AaBb Ccl AaBb CcD
T Normal T No Spaci... Heading 1 Heading 2 Heading 3
Title
Subtitle Subtle Em...
Styles
N
14. Which of the following element of feasibility analysis that involves an analysis of the cash flow
profile of the project?
a. Cost estimate
b. Financial analysis
c. Project estimates
d. Process work
15. The following statements are disadvantages of PERT/CPM except for:
a. It produces a diagram that makes it easy to see dependencies and the critical path.
b. There can be potentially hundreds or thousands of activities and individual dependency
relationships.
c. The lack of a timeframe on most PERT/CPM charts makes it harder to show status
although colors can help (e.g., specific color for completed nodes).
d. When the PERT/CPM charts become unwieldy, they are no longer used to manage the
project.
A
Changel
Styles
30°C
0
X
Activate Windows
Go to Settings to activate Windows.
+
11:37 PM
9/24/2022
BR 60%
Find
ab
ac Replace
Select
Editing
?
Transcribed Image Text:Cin Paste H 155 = Home Cut E Copy ✔Format Painter Clipboard Insert Page: 3 of 4 Words: 39 HH G Page Layout Calibri (Body) BIU Type here to search References - 11 abe X, X Aa Font Mailings Aal Review Α Α΄ B-B-S $ENT Paragraph 8. Which of the following statements is NOT TRUE with Extreme Programming? a. The key emphases of eXtreme Programming are its use of two-person programming teams and having a customer on-site during the development process. b. With XP, analysis and design phases of the life cycle link into a series of activities based on the basic processes of coding, testing, listening, and designing. View c. In XP, coding and testing are related parts of the same process, which means the programmers who write the code can also develop the tests. d. The overall philosophy of XP is that code will be integrated into the system it is being developed for and tested within a few hours after it has been written. 9. Which of the following is an advantage of rapid application development? a. It allows for the simultaneous gathering and consolidating of large amounts of information. a. I, II, and III b. I and II only c. I and III only d. II and III only b. Software engineers can start working on the project earlier rather than wading through a lengthy early design process. c. It is useful for projects in which the user requirements are uncertain or not precise. d. Assists in identifying any problems with the efficacy of earlier design, requirements analysis and coding activities. SAD Chapter quiz 1 - Microsoft Word 10. Which of the following is a drawback of spiral model? a. It does not accept the expected changes and revisions that become necessary with most projects. b. Estimation of budget and time are harder to judge at the beginning of the project since the requirements evolve through the process. c. It opens up many scope of inter-personal conflict. d. It allows for the simultaneous gathering and consolidating of large amounts of information. 11. Which of the following is NOT a driving force in project initiation? a. To respond to an opportunity b. To resolve a problemy c. To conform to a directive d. To increase market share 12. Which of the following is a process in developing a cost-benefit analysis? 1. Estimate the anticipated development and operational costs. II. Estimate the anticipated financial benefits. II. Estimate of costs and benefits. O 13. Which of the following is the purpose of technical feasibility? a. To measure how well the solution will work in the organization and how people feel about the system/project. b. For systems analyst to gain understanding of the likelihood that all potential time frames and completion date schedules can be met and that meeting these dates will be sufficient for dealing with the needs of the organization. To gain understanding of the organization's ability to construct the proposed system. All of the hous HI AaBb CcDc AaBb CcDc Aa Bbc AaBb AaBb CCD AaB AaBb Ccl AaBb CcD T Normal T No Spaci... Heading 1 Heading 2 Heading 3 Title Subtitle Subtle Em... Styles N 14. Which of the following element of feasibility analysis that involves an analysis of the cash flow profile of the project? a. Cost estimate b. Financial analysis c. Project estimates d. Process work 15. The following statements are disadvantages of PERT/CPM except for: a. It produces a diagram that makes it easy to see dependencies and the critical path. b. There can be potentially hundreds or thousands of activities and individual dependency relationships. c. The lack of a timeframe on most PERT/CPM charts makes it harder to show status although colors can help (e.g., specific color for completed nodes). d. When the PERT/CPM charts become unwieldy, they are no longer used to manage the project. A Changel Styles 30°C 0 X Activate Windows Go to Settings to activate Windows. + 11:37 PM 9/24/2022 BR 60% Find ab ac Replace Select Editing ?
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY