6.4: An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order.
6.4: An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![6.4:
An order for 50 of a product is processed on work centers A and B. The setup time on A is 45
minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run
time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time
between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into
stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total
manufacturing lead time for the order.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F5a99bae1-6366-4edc-b05f-bae669e813bc%2F00ebe3fc-278b-48a8-9cc0-7561eff1c04a%2Fo6pf47b_processed.png&w=3840&q=75)
Transcribed Image Text:6.4:
An order for 50 of a product is processed on work centers A and B. The setup time on A is 45
minutes, and run time is 5 minutes per piece. The setup time on B is 30 minutes, and the run
time is 4 minutes per piece. Wait time between the two operations is 8 hours. The move time
between A and B is 60 minutes. Wait time after operation B is 8 hours, and the move time into
stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total
manufacturing lead time for the order.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.