6-64. (Job shop scheduling) Three jobs, J1, J2, and J3, are processed on three machines, M1, M2, and M3, according to the following sequences (processing times are shown in parentheses): J1: M3(3) M1(4) - M2(6) J2: M2(1) M3(5) – M2(9) J3: M3(8) M2(8) – M1(7) The order in which the jobs are processed on the different machines is predetermined as: M1: J1 J2 J3 M2: J2 J3 - J1 M3: J3 J1 - J2 a. Represent the problem as a CPM network for which the critical path determines the make span of all three jobs. b. Use the critical path calculations to develop the scheduling of the jobs (Gantt chart), assuming that each operation is scheduled at its earliest start time.

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
Kindly give me a nuanced response. I want to understand what is being done so I can replicate. Thank you very much.
6-64. (Job shop scheduling) Three jobs, J1, J2, and J3, are processed on three
machines, M1, M2, and M3, according to the following sequences (processing
times are shown in parentheses):
J1: M3(3)
M1(4) - M2(6)
J2: M2(1)
M3(5) – M2(9)
J3: M3(8)
M2(8) – M1(7)
The order in which the jobs are processed on the different machines is
predetermined as:
M1: J1 J2 J3
M2: J2
J3 - J1
M3: J3
J1 - J2
a. Represent the problem as a CPM network for which the critical path
determines the make span of all three jobs.
b. Use the critical path calculations to develop the scheduling of the jobs
(Gantt chart), assuming that each operation is scheduled at its earliest
start time.
Transcribed Image Text:6-64. (Job shop scheduling) Three jobs, J1, J2, and J3, are processed on three machines, M1, M2, and M3, according to the following sequences (processing times are shown in parentheses): J1: M3(3) M1(4) - M2(6) J2: M2(1) M3(5) – M2(9) J3: M3(8) M2(8) – M1(7) The order in which the jobs are processed on the different machines is predetermined as: M1: J1 J2 J3 M2: J2 J3 - J1 M3: J3 J1 - J2 a. Represent the problem as a CPM network for which the critical path determines the make span of all three jobs. b. Use the critical path calculations to develop the scheduling of the jobs (Gantt chart), assuming that each operation is scheduled at its earliest start time.
Expert Solution
steps

Step by step

Solved in 2 steps with 6 images

Blurred answer
Similar questions
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,