•• 5.22 Sox Engineering designs and constructs air conditic ing and heating systems for hospitals and clinics. Currently, t company's staff is overloaded with design work. There is a maj design project due in 8 weeks. The penalty for completing t design late is $14,000 per week because any delay will cause t facility to open later than anticipated and cost the client signi cant revenue. If the company uses its inside engineers to comple the design, it will have to pay them overtime for all work. S has estimated that it will cost $12,000 per week (wages and ov head), including late weeks, to have company engineers comple the design. Sox is also considering having an outside engineeri firm do the design. A bid of $90,000 has been received for t completed design. Yet another option for completing the design to conduct a joint design by having a third engineering compa- complete all electromechanical components of the design at a ce of $50,000. Sox would then complete the rest of the design a control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completi. the project within various time frames when using each of t three options. Those estimates are shown in the following table PROBABILITY OF COMPLETING THE DESIGN ON 1 WEEK LATE 2 WEEKS 3 WEEK LATE ΟΡTION TIME LATE Internal Engineers 4 .5 .1 External Engineers .2 .4 .3 .1 Joint Design .1 .3 4 2 What is the best decision based on an expected monetary val (EMV) criterion? (Note: You want the lowest EMV because are dealing with costs in this prohlem) Px
•• 5.22 Sox Engineering designs and constructs air conditic ing and heating systems for hospitals and clinics. Currently, t company's staff is overloaded with design work. There is a maj design project due in 8 weeks. The penalty for completing t design late is $14,000 per week because any delay will cause t facility to open later than anticipated and cost the client signi cant revenue. If the company uses its inside engineers to comple the design, it will have to pay them overtime for all work. S has estimated that it will cost $12,000 per week (wages and ov head), including late weeks, to have company engineers comple the design. Sox is also considering having an outside engineeri firm do the design. A bid of $90,000 has been received for t completed design. Yet another option for completing the design to conduct a joint design by having a third engineering compa- complete all electromechanical components of the design at a ce of $50,000. Sox would then complete the rest of the design a control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completi. the project within various time frames when using each of t three options. Those estimates are shown in the following table PROBABILITY OF COMPLETING THE DESIGN ON 1 WEEK LATE 2 WEEKS 3 WEEK LATE ΟΡTION TIME LATE Internal Engineers 4 .5 .1 External Engineers .2 .4 .3 .1 Joint Design .1 .3 4 2 What is the best decision based on an expected monetary val (EMV) criterion? (Note: You want the lowest EMV because are dealing with costs in this prohlem) Px
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
show the complete solution
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 1 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.