•• 5.22 Sox Engineering designs and constructs air conditic ing and heating systems for hospitals and clinics. Currently, t company's staff is overloaded with design work. There is a maj design project due in 8 weeks. The penalty for completing t design late is $14,000 per week because any delay will cause t facility to open later than anticipated and cost the client signi cant revenue. If the company uses its inside engineers to comple the design, it will have to pay them overtime for all work. S has estimated that it will cost $12,000 per week (wages and ov head), including late weeks, to have company engineers comple the design. Sox is also considering having an outside engineeri firm do the design. A bid of $90,000 has been received for t completed design. Yet another option for completing the design to conduct a joint design by having a third engineering compa- complete all electromechanical components of the design at a ce of $50,000. Sox would then complete the rest of the design a control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completi. the project within various time frames when using each of t three options. Those estimates are shown in the following table PROBABILITY OF COMPLETING THE DESIGN ON 1 WEEK LATE 2 WEEKS 3 WEEK LATE ΟΡTION TIME LATE Internal Engineers 4 .5 .1 External Engineers .2 .4 .3 .1 Joint Design .1 .3 4 2 What is the best decision based on an expected monetary val (EMV) criterion? (Note: You want the lowest EMV because are dealing with costs in this prohlem) Px
•• 5.22 Sox Engineering designs and constructs air conditic ing and heating systems for hospitals and clinics. Currently, t company's staff is overloaded with design work. There is a maj design project due in 8 weeks. The penalty for completing t design late is $14,000 per week because any delay will cause t facility to open later than anticipated and cost the client signi cant revenue. If the company uses its inside engineers to comple the design, it will have to pay them overtime for all work. S has estimated that it will cost $12,000 per week (wages and ov head), including late weeks, to have company engineers comple the design. Sox is also considering having an outside engineeri firm do the design. A bid of $90,000 has been received for t completed design. Yet another option for completing the design to conduct a joint design by having a third engineering compa- complete all electromechanical components of the design at a ce of $50,000. Sox would then complete the rest of the design a control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completi. the project within various time frames when using each of t three options. Those estimates are shown in the following table PROBABILITY OF COMPLETING THE DESIGN ON 1 WEEK LATE 2 WEEKS 3 WEEK LATE ΟΡTION TIME LATE Internal Engineers 4 .5 .1 External Engineers .2 .4 .3 .1 Joint Design .1 .3 4 2 What is the best decision based on an expected monetary val (EMV) criterion? (Note: You want the lowest EMV because are dealing with costs in this prohlem) Px
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
show the complete solution

Transcribed Image Text:•• 5.22
ing and heating systems for hospitals and clinics. Currently, the
company's staff is overloaded with design work. There is a major
design project due in 8 weeks. The penalty for completing the
design late is $14,000 per week because any delay will cause the
facility to open later than anticipated and cost the client signifi-
cant revenue. If the company uses its inside engineers to complete
the design, it will have to pay them overtime for all work. Sox
has estimated that it will cost $12,000 per week (wages and over-
head), including late weeks, to have company engineers complete
the design. Sox is also considering having an outside engineering
firm do the design. A bid of $90,000 has been received for the
completed design. Yet another option for completing the design is
to conduct a joint design by having a third engineering company
complete all electromechanical components of the design at a cost
of $50,000. Sox would then complete the rest of the design and
control systems at an estimated cost of $30,000.
Sox has estimated the following probabilities of completing
the project within various time frames when using each of the
three options. Those estimates are shown in the following table:
Sox Engineering designs and constructs air condition-
PROBABILITY OF COMPLETING THE DESIGN
ON
TIME
2 WEEKS 3 WEEKS
LATE
1 WEEK
OPTION
LATE
LATE
Internal Engineers
4
5
.1
External Engineers
.2
.4
.3
.1
Joint Design
.1
.3
4
.2
What is the best decision based on an expected monetary value
(EMV) criterion? (Note: You want the lowest EMV because we
are dealing with costs in this problem.) X
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.