5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job # 181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities BC DE EF 1 Cost to Crash 1 Week P 8,000 10,000 8,800 b. Compute for the cost to crash of the activities. Cost to Crash 2 Weeks P15,000 19,600 19,500
5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job # 181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities BC DE EF 1 Cost to Crash 1 Week P 8,000 10,000 8,800 b. Compute for the cost to crash of the activities. Cost to Crash 2 Weeks P15,000 19,600 19,500
Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
Related questions
Question

Transcribed Image Text:5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is
currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.
Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal
completion time of 22 weeks. The following activities can be crashed.
Activities
Cost to Crash 1 Week
P 8.000
Cost to Crash 2 Weeks
P15,000
19,600
19,500
BC
DE
EF
10,000
8,800
b. Compute for the cost to crash of the activities.
(United States)
56.8%
26
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 29 images

Recommended textbooks for you

Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated

Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education

Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY

Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated

Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education

Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY

Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,