45 m taped distance A surveyor used 75-meter line AB to compute his pace factor. The following are his number of paces: 88.00, 89.00, 88.00, 87.00, 89.00, 90.00, 86.00, 87.00, 90.00, 91.00 At day 1, he also went on to measure Line CD. The following are his number of paces: 512.00, 510.00, 520.00, 511.00, 512.00, 515.00, 516.00, 510.00, 518.00, 510.00 At day 2, the following are his number of paces for Line CD: 510.00, 515.00, 511.00, 509.00, 504.00, 512.00, 515.00, 508.00, 509.00, 510.00 At day 3, the following are his number of paces for Line CD: 517.00, 518.00, 521.00, 525.00, 512.00, 522.00, 520.00, 512.00, 518.00, 517.00 What is the residual of the measurement of Line CD in day 1?
45 m taped distance A surveyor used 75-meter line AB to compute his pace factor. The following are his number of paces: 88.00, 89.00, 88.00, 87.00, 89.00, 90.00, 86.00, 87.00, 90.00, 91.00 At day 1, he also went on to measure Line CD. The following are his number of paces: 512.00, 510.00, 520.00, 511.00, 512.00, 515.00, 516.00, 510.00, 518.00, 510.00 At day 2, the following are his number of paces for Line CD: 510.00, 515.00, 511.00, 509.00, 504.00, 512.00, 515.00, 508.00, 509.00, 510.00 At day 3, the following are his number of paces for Line CD: 517.00, 518.00, 521.00, 525.00, 512.00, 522.00, 520.00, 512.00, 518.00, 517.00 What is the residual of the measurement of Line CD in day 1?
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
45 m taped distance
A surveyor used 75-meter line AB to compute his pace factor. The following are his number of paces:
88.00, 89.00, 88.00, 87.00, 89.00, 90.00, 86.00, 87.00, 90.00, 91.00
At day 1, he also went on to measure Line CD. The following are his number of paces:
512.00, 510.00, 520.00, 511.00, 512.00, 515.00, 516.00, 510.00, 518.00, 510.00
At day 2, the following are his number of paces for Line CD:
510.00, 515.00, 511.00, 509.00, 504.00, 512.00, 515.00, 508.00, 509.00, 510.00
At day 3, the following are his number of paces for Line CD:
517.00, 518.00, 521.00, 525.00, 512.00, 522.00, 520.00, 512.00, 518.00, 517.00
What is the residual of the measurement of Line CD in day 1?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning