4. Calculate the percentage of completion during 20x5

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

PLEASE ANSWER THE NO. 4 QUESTION

In 20x5, Chicago Construction began work on a three-year construction project to build a new
IX - Incomplete Data
performing arts complex (the "PAC"). The PAC contract price is P150 million. Chicago usehew
percentage-of-completion method of accounting. At the end of 20x5, the following fine Ihe
statement information indicates the results to date for the PAC:
Income Statement:
Revenue
Cost of Construction.
Gross profit.
P 2 million
35 million
P ?million
Balance Sheet:
Accounts Receivable from construction billings.
Construction in progress.
Less: Billings on construction
Net billings in excess of construction in progress
Cash Flow Statement
P 14 million
P.50 million
(P ? million)
P million
Cash Collections
P 46 million
Required: Compute the following, placing your answer in the spaces provided and showing
supporting computations below:
1. Total revenue recognized during 20x5
2. Billings on construction
3. Net in excess of construction in progress
4. Calculate the percentage of completion during 20x5
Transcribed Image Text:In 20x5, Chicago Construction began work on a three-year construction project to build a new IX - Incomplete Data performing arts complex (the "PAC"). The PAC contract price is P150 million. Chicago usehew percentage-of-completion method of accounting. At the end of 20x5, the following fine Ihe statement information indicates the results to date for the PAC: Income Statement: Revenue Cost of Construction. Gross profit. P 2 million 35 million P ?million Balance Sheet: Accounts Receivable from construction billings. Construction in progress. Less: Billings on construction Net billings in excess of construction in progress Cash Flow Statement P 14 million P.50 million (P ? million) P million Cash Collections P 46 million Required: Compute the following, placing your answer in the spaces provided and showing supporting computations below: 1. Total revenue recognized during 20x5 2. Billings on construction 3. Net in excess of construction in progress 4. Calculate the percentage of completion during 20x5
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Diagnostic Coding: Icd 10 cm
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education