2. In the CPM network, the critical path has six activities. Their durations are tabulated next. Activity Optimistic Most Likely A C Q S N K 3 4 5 3 7 4 5 8 7 5 10 5 Pessimistic 6 13 8 7 15 8 Compute the following: a. The probability that the project will finish by the end of day 36 b. The probability that the project will finish by the end of day 39 c. The probability that the project will finish before day 38 d. The probability that the project will finish on the 35th day e. The completion date with at least a 95% confidence level.
2. In the CPM network, the critical path has six activities. Their durations are tabulated next. Activity Optimistic Most Likely A C Q S N K 3 4 5 3 7 4 5 8 7 5 10 5 Pessimistic 6 13 8 7 15 8 Compute the following: a. The probability that the project will finish by the end of day 36 b. The probability that the project will finish by the end of day 39 c. The probability that the project will finish before day 38 d. The probability that the project will finish on the 35th day e. The completion date with at least a 95% confidence level.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
This is an engineering project management question

Transcribed Image Text:In the CPM network, the critical path has six activities. Their durations are tabulated below:
| Activity | Optimistic | Most Likely | Pessimistic |
|----------|------------|-------------|-------------|
| A | 3 | 5 | 6 |
| C | 4 | 8 | 13 |
| Q | 5 | 7 | 8 |
| S | 3 | 5 | 7 |
| N | 7 | 10 | 15 |
| K | 4 | 5 | 8 |
Compute the following:
a. The probability that the project will finish by the end of day 36
b. The probability that the project will finish by the end of day 39
c. The probability that the project will finish before day 38
d. The probability that the project will finish on the 35th day
e. The completion date with at least a 95% confidence level.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 2 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning