2 + 5 Project Start Activity # Duration ABCD 5 10 5 10 A D F E 10 F 15 G 5 H 5 10 155 0 0 0 0 0 0 B E Activity ID ES Duration EF LS TF Act No. LF FINSIH

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter4: Mechanical Processes
Section: Chapter Questions
Problem 4.22P: Why is it so difficult to process MSW?
Question

fill in the graph and color critical path red

 

please help

2
+
5
Project Start
Activity #
Duration
ABCD
5
10
5
10
A
D
F
E
10
F
15
G
5
H
5
10
155
0
0
0
0
0
0
B
E
Activity ID
ES Duration EF
LS
TF
Act No.
LF
FINSIH
Transcribed Image Text:2 + 5 Project Start Activity # Duration ABCD 5 10 5 10 A D F E 10 F 15 G 5 H 5 10 155 0 0 0 0 0 0 B E Activity ID ES Duration EF LS TF Act No. LF FINSIH
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,