2-42 A new integrated computer system is to be installed worldwide for a major corporation. Bids on this project are being solicited, and the contract will be awarded to one of the bidders. As a part of the pro- posal for this project, bidders must specify how long the project will take. There will be a significant pen- alty for finishing late. One potential contractor de- termines that the average time to complete a project of this type is 40 weeks with a standard deviation of 5 weeks. The time required to complete this project is assumed to be normally distributed. (a) If the due date of this project is set at 40 weeks, what is the probability that the contractor will have to pay a penalty (i.e., the project will not be finished on schedule)? (b) If the due date of this project is set at 43 weeks, what is the probability that the contractor will have to pay a penalty (i.e., the project will not be finished on schedule)? (c) If the bidder wishes to set the due date in the proposal so that there is only a 5% chance of be- ing late (and consequently only a 5% chance of having to pay a penalty), what due date should

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
2-42 A new integrated computer system is to be installed
worldwide for a major corporation. Bids on this
project are being solicited, and the contract will be
awarded to one of the bidders. As a part of the pro-
posal for this project, bidders must specify how long
the project will take. There will be a significant pen-
alty for finishing late. One potential contractor de-
termines that the average time to complete a project
of this type is 40 weeks with a standard deviation of
5 weeks. The time required to complete this project
is assumed to be normally distributed.
(a) If the due date of this project is set at 40 weeks,
what is the probability that the contractor will
have to pay a penalty (i.e., the project will not be
finished on schedule)?
(b) If the due date of this project is set at 43 weeks,
what is the probability that the contractor will
have to pay a penalty (i.e., the project will not be
finished on schedule)?
(c) If the bidder wishes to set the due date in the
proposal so that there is only a 5% chance of be-
ing late (and consequently only a 5% chance of
having to pay a penalty), what due date should
be set?
Transcribed Image Text:2-42 A new integrated computer system is to be installed worldwide for a major corporation. Bids on this project are being solicited, and the contract will be awarded to one of the bidders. As a part of the pro- posal for this project, bidders must specify how long the project will take. There will be a significant pen- alty for finishing late. One potential contractor de- termines that the average time to complete a project of this type is 40 weeks with a standard deviation of 5 weeks. The time required to complete this project is assumed to be normally distributed. (a) If the due date of this project is set at 40 weeks, what is the probability that the contractor will have to pay a penalty (i.e., the project will not be finished on schedule)? (b) If the due date of this project is set at 43 weeks, what is the probability that the contractor will have to pay a penalty (i.e., the project will not be finished on schedule)? (c) If the bidder wishes to set the due date in the proposal so that there is only a 5% chance of be- ing late (and consequently only a 5% chance of having to pay a penalty), what due date should be set?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Labor Cost
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education