15.21 A moving belt line is used to assemble a product whose work content = 22 min. Production rate = 35 units/hr, and the proportion uptime 0.96. The length of each station = 2.0 m and station manning level = 1.0 for all stations. The belt speed can be set at any value between 0.6 and 3.0 m/min. It is expected that the balance delay will be about 0.08 or slightly higher. Time lost for repositioning each cycle is 6 sec. (a) Determine the number of stations needed on the line. (b) Using a tolerance time that is 50% greater than the cycle time, what would be an appropriate belt speed and spacing between parts?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
15.21 A moving belt line is used to assemble a product whose work content = 22 min. Production rate =
35 units/hr, and the proportion uptime = 0.96. The length of each station = 2.0 m and station manning
level = 1.0 for all stations. The belt speed can be set at any value between 0.6 and 3.0 m/min. It is
expected that the balance delay will be about 0.08 or slightly higher. Time lost for repositioning each
cycle is 6 sec. (a) Determine the number of stations needed on the line. (b) Using a tolerance time that is
!!
%!
50% greater than the cycle time, what would be an appropriate belt speed and spacing between parts?
Transcribed Image Text:15.21 A moving belt line is used to assemble a product whose work content = 22 min. Production rate = 35 units/hr, and the proportion uptime = 0.96. The length of each station = 2.0 m and station manning level = 1.0 for all stations. The belt speed can be set at any value between 0.6 and 3.0 m/min. It is expected that the balance delay will be about 0.08 or slightly higher. Time lost for repositioning each cycle is 6 sec. (a) Determine the number of stations needed on the line. (b) Using a tolerance time that is !! %! 50% greater than the cycle time, what would be an appropriate belt speed and spacing between parts?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.