10-29 Learning curve, incremental unit-time learning model. Assume the same information for Northern Defense as in Exercise 10-28, except that Northern Defense uses an 85% incremental unit-time learning model as a basis for predicting direct manufacturing labor-hours. (An 85% learning curve means b = -0.234465.) Calculate the total variable costs of producing 2, 3, and 4 units. If you solved Exercise 10-28, compare your cost predictions in the two exercises for 2 and 4 units. Why are the predictions different? How should Northern Defense decide which model it should use?
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
10-29 Learning curve, incremental unit-time learning model. Assume the same information for Northern Defense as in Exercise 10-28, except that Northern Defense uses an 85% incremental unit-time learning model as a basis for predicting direct manufacturing labor-hours. (An 85% learning curve means b = -0.234465.)
- Calculate the total variable costs of producing 2, 3, and 4 units.
- If you solved Exercise 10-28, compare your cost predictions in the two exercises for 2 and 4 units. Why are the predictions different? How should Northern Defense decide which model it should use?