10. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the fırst activity assigned to workstation 3? 0.2 0.4 0.2 1.2 b a 0.4 1.0 2.0 d g O b Ос O f a None of the provided options

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

10. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the first activity assigned to workstation 3?

b
c
d
f
e
a
**Question:**

10. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the first activity assigned to workstation 3?

**Diagram:**

The precedence network diagram includes the following nodes and paths:

- Node `a` with a duration of 0.2 minutes, leading to node `b`.
- Node `b` with a duration of 0.4 minutes, leading to node `c`.
- Node `c` with a duration of 0.2 minutes, leading to node `f`.
- Node `d` with a duration of 0.4 minutes, leading to node `e`.
- Node `e` with a duration of 1.0 minute, leading to node `g`.
- Node `f` with a duration of 1.2 minutes, leading to node `g`.
- Node `g` with a duration of 2.0 minutes.

The diagram shows the flow of tasks from one to the next, indicating the order of assembly and the time each task takes.

**Answer Options:**

- ○ b
- ○ c
- ○ d
- ○ f
- ○ e
- ○ a
- ● None of the provided options

The correct answer is already selected as "None of the provided options," which suggests that the first activity assigned to workstation 3 is not listed among the provided options.
Transcribed Image Text:**Question:** 10. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the first activity assigned to workstation 3? **Diagram:** The precedence network diagram includes the following nodes and paths: - Node `a` with a duration of 0.2 minutes, leading to node `b`. - Node `b` with a duration of 0.4 minutes, leading to node `c`. - Node `c` with a duration of 0.2 minutes, leading to node `f`. - Node `d` with a duration of 0.4 minutes, leading to node `e`. - Node `e` with a duration of 1.0 minute, leading to node `g`. - Node `f` with a duration of 1.2 minutes, leading to node `g`. - Node `g` with a duration of 2.0 minutes. The diagram shows the flow of tasks from one to the next, indicating the order of assembly and the time each task takes. **Answer Options:** - ○ b - ○ c - ○ d - ○ f - ○ e - ○ a - ● None of the provided options The correct answer is already selected as "None of the provided options," which suggests that the first activity assigned to workstation 3 is not listed among the provided options.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Facility layout
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.