1- The number of critical paths in the project is All options are incorrect O
Q: a small project consisting of eight activities has the following characteristics:…
A: Note: - As we can answer only up to three subparts we will answer the first three subparts of part…
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: Explain
A: The above project matrix is a planned approach to focus on important tasks which are important for…
Q: c. Suppose that the indirect costs of the project amount to $200 per day. Find theoptimal number of…
A: Given Data Activity Immediate Predecessor Normal Time Expedited Time Normal Cost Expedited…
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: Q1: For activities shown in table below, find the new time of project after updating, if the project…
A: Given data is
Q: (a) You have just been nominated as a project manager for a project. The objective is to manufacture…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: i. What is the project completion date? ii. What is the total cost required for completing this…
A: Total cost is the cost that includes fixed cost and variable cost of goods and services.
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: Why might the critical path change during a project? What happens if the critical path does change?
A: A critical task might be described as a task that must be met on a plan for the project to complete…
Q: 2/ For the project data shown in the table below. If it was decided to turn over the project at 34…
A: Given data is
Q: 2. Reduce job 3 by two days. ONo O Yes 3. Reduce job 5 by two days. Yes O No e. What is the…
A: Given Information: Critical Path:- 1-2-5-8-9-11 Expected Completion Time:- 26.5 days
Q: 4- Standard Deviation Value For the critical path in the project is
A:
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: d. The partners have decided that shortening the project by two days would be beneficial, as long as…
A:
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: From the network diagram, The possible paths and their duration are: A-D-G-H = 3+3+1+3 = 10B-E-F =…
Q: What is not from the following a part of project phases a. Execution O b. Planning O c. Initiation O…
A: "Since, you have asked multiple questions so we will solve the first question for you. If you want…
Q: Financial methods provide objective analysis for project selection. Select one: a. True O b. False
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Q: TABLE 1: Activities and duration project Duration in weeks Activity Proceeding activity Optimistic…
A:
Q: Q1(d) Explain, what does it means if the priorities of a project include: Time- enhance,…
A: This question is related to topic-project management and this topic falls under the operations…
Q: Given the activities of a project, their tim redecessors shown below: 1. Draw the Gannt chart for…
A: Given: Activities Activity Times, months Immediate predecessors Maximum slack moths A 2 - B…
Q: 3. Highlight the total time to complete the project (days) 4. Calculate the late finishing time…
A: The total time to complete a project can be calculated as the sum of the critical paths so, the…
Q: c. What is the expected project completion time? (Do not round intermediate calculations. Round your…
A: Find the duration calculations below:
Q: Who creates the project schedule?
A: Project scheduling refers to creating a schedule containing the activities, milestones, and…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: What is the importance of variance analysis to project managers?
A: Variance analysis can be summed up as an analysis of the distinction between arranged and genuine…
Q: (2) In the context of project management, why is it important to manage risks?
A: Every organization faces unknown risks or harmful events that can devastate the company's finances…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: What’s the significance of identifying the critical path?
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: The project network diagram is the diagram that shows the activity and the project duration to…
Q: 1. Explain the importance of a critical path in a project plan.
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: 3- The value of the variance of the critical path in the project is
A: Variance = square of sum standard deviations of critical activities Standard deviation = (b-a)/6
Q: Explain the importance of a PERT diagram in a project plan.
A: PERT or Project Evaluation Review Technique in project management (PM) applies to a method that is…
Q: How long will the following project take to complete? Task Predecessor Time (days) A None 100 B A 50…
A: In order to find how much time it would take for the project to finish we need to find the Critical…
Q: a. Why is risk identification important to a project? b. Give 3 examples how IT/MIS tools can…
A: Risks are unexpected events that might affect the business either in a positive or negative manner.…
Q: NORMAL CRASH TIME NORMAL CRASH COST TIME IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST PREDECESSOR(S) A 4…
A: Answer: we can see that for the mentioned project there are seven activities A, B, C, D, E, F, G. In…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: Project Evaluation and Review Technique (PERT) may be a technique utilized in project management…
Q: 8- The probability of completing the project in a time greater than the critical path time plus 2…
A: The probability is seen corresponding to z-score under normal distribution is considered in the…
Q: parameters of the ch
A: Project management An important part of managing projects is knowing how to manage them effectively.…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
![Before answering the following questions, you must draw
the arrow diagram, rectangles, network calculations, and
the project diagram, the details of which are shown in the
table below.
Time (week)
Activity Dependency
Resource
b
a
m
1.5
2
2.5
3
2
2.5
3
2
3
А, В
1.5
2
2.5
2
0.5
1
1.5
2
1
2
3
D, E
C, F, G
C, G
G
3.5
3
3
4
1.5
2
2.5
2
1- The number of critical paths in the project is
All options are incorrect
7
2
3
4
8
3765
ABCDEECHI](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F15fb8c87-2a80-4253-b764-584dcae012d2%2Ffc65b746-17f5-4f5a-9983-c94f6330c72c%2Fcu9v34q_processed.jpeg&w=3840&q=75)
![](/static/compass_v2/shared-icons/check-mark.png)
Step by step
Solved in 3 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…1.You’re managing a project to install 400 windows in a new skyscraper and need to figure outyour budget. Each week of the project costs the same: your team members are paid a total of $4,000every week, and you need $2,000 worth of parts each week to do the work. If the project isscheduled to last 16 weeks, calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project? 2.You’re managing a highway construction project. Your total budget is $650,000, and there isa total of 7,500 hours of work scheduled on the project. You check with your accountingdepartment, and they tell you that you’ve spent a total of $400,000. According to the schedule,your crew should have worked 4,500 hours, but your foreman says that the crew was allowed towork some overtime, and they’ve put in 5,100 hours of work. Calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project?
- Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.An enterprise resource planning (ERP) system is best described as: Answers A E A An information system designed to allocate resources, such as staff and rooms, to an organisation's current projects B The software and hardware required to allow functional area information systems to exchange information C An information system that enables an organisation to plan the resources required for upcoming projects DA method to enable legacy departmental information systems to interoperate with newer systems. EA suite of integrated software modules for managing information about business activities.You are working in the planning team of a food factory in Malaysia, producing Lipton. Tomorrow is the deadline for shipping deliveries to Giant supermarkets ready for a new Lipton promotion. The promotion has featured an extensive social media campaign to drive sales. You have just been informed that the delivery of raw materials has broken down. There is a risk that the tight manufacturing schedule will not be feasible in the time remaining. So in this case, 1-Who dod you need to keep informed? 2. What method of communication would you choose for each?
- Which of the following are contractual terms (Select all that apply) NDA MOU LOI MAO CCB Communication can include which of the following Kick-off meetings Listening Outward E-mail All of the above Risk activities should be assigned To a team After a trigger occurs Without being added to the Risk Register To a single person In priority order What does CV stand for and what does it mean? (Select all that apply) Cost Variance, calculated EV – AC Continuous variability, measure of process Cost Variance, <1 is over budget Cost Variance, >1 is over budget Cost Variance, calculated AC – EVDave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managers++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)