1 2 3 4 The manager, Jenny has designed the schedule for a renovation project. The jobs involved and their start and finish (or end) dates are listed in Table 3. Answer the questions below, Q1 Q3. How the days are counted to determine the end date can be understood by this example: If a job starts at 3/1/2024 and is expected to take 3 days, the finish/end date will be 3/4/2024 (i.e. one processing day goes from one day to the next day). 5 6 Q1: Create the Gantt chart for Jenny's schedule (i.e., Table 3). The origin of the time axis should be labeled as 3/1/2024. 7 8 9 Table 3-Jenny's schedule 10 Job label Job description Start date End date 11 A Select staff members 3/15/24 3/27/24 12 B Survey 3/16/24 3/25/24 13 с Select equipment 4/7/24 4/17/24 14 D Prepare final plan 3/26/24 4/5/24 15 E Bring utilities to site 4/1/24 4/25/24 16 F Interview applicants 3/28/24 4/7/24 17 G Purchase/deliver equipment 4/12/24 5/16/24 18 H Renovation 4/5/24 5/15/24 19 | Update infomation system 3/30/24 4/14/24 20 J Install equipment 5/17/24 5/20/24 21 K Train new staff 5/22/24 5/28/24 22
1 2 3 4 The manager, Jenny has designed the schedule for a renovation project. The jobs involved and their start and finish (or end) dates are listed in Table 3. Answer the questions below, Q1 Q3. How the days are counted to determine the end date can be understood by this example: If a job starts at 3/1/2024 and is expected to take 3 days, the finish/end date will be 3/4/2024 (i.e. one processing day goes from one day to the next day). 5 6 Q1: Create the Gantt chart for Jenny's schedule (i.e., Table 3). The origin of the time axis should be labeled as 3/1/2024. 7 8 9 Table 3-Jenny's schedule 10 Job label Job description Start date End date 11 A Select staff members 3/15/24 3/27/24 12 B Survey 3/16/24 3/25/24 13 с Select equipment 4/7/24 4/17/24 14 D Prepare final plan 3/26/24 4/5/24 15 E Bring utilities to site 4/1/24 4/25/24 16 F Interview applicants 3/28/24 4/7/24 17 G Purchase/deliver equipment 4/12/24 5/16/24 18 H Renovation 4/5/24 5/15/24 19 | Update infomation system 3/30/24 4/14/24 20 J Install equipment 5/17/24 5/20/24 21 K Train new staff 5/22/24 5/28/24 22
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
show me step by step in excel what I need to do to make the gantt chart for q1
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.