SellBuy eCommerce Project PROJECT PLAN V5 Pear Development Studio Team: Caleb Smith, Jaleel Harris, Scarlet Mendoza, Deborah Bagunda Instructor: Professor Ade Thompson Course: CIST 2931 - Advanced Systems Project Date: October 29, 2023
SOFTWARE DEVELOPMENT PROJECT PLAN PROJECT NAME SellBuy eCommerce PROJECT MANAGER Jaleel Harris PROJECT DELIVERABLE During this week: - Test Plan Deliverable: The test plan describes how the tester will verify that the system works as intended. - Project Plan V5: The third version of the project plan will be an updated version of the previous plans. - Weekly Progress Report V6: The progress report will be done individually and will show the progress of the project. SCOPE STATEMENT 1. Stakeholder Survey: This survey was done in order to investigate and research information which will affect our project. 2. Requirement Management: This is done with the purpose of figuring out all the requirements of the project. 3. Scope Document: The Scope Document includes a detailed description of the project, its objectives and the deliverables which will be produced during the course of the project. 4. Work Breakdown Structure: The WBS breaks down the work of the project into smaller sections. 5. Weekly Progress Report Plan V1: The first version of the Weekly Progress Report Plan was completed by each team member to view the progress made this week. 6. Team Meeting Plan: The Team Meeting Plan is done to ensure every team member knows what their job is for that week. 7. Project Schedule: The Project Schedule is made based on previous documents like the Scope Document.
8. Project Management Plan: Every week, the Project Plan will be updated. 9. Project Plan Document V2: The second version of the project plan will be completed and turned in. 10. Functional and Nonfunctional Requirements: The requirements of the project will be discussed and written down on a document. 11. UML Diagram: The UML diagram for the system will be worked on. 12. Database UML Diagram: The UML for the database will be worked on. 13. Weekly Progress Report V3: The individual progress report will be completed and turned in. 14. Use Case Analysis: The Use Case Analysis will include information about the users, the product, and their interactions. 15. Weekly Progress Report V4: The fourth version of the progress report will be done individually. 16. Project Plan Document V3: The updated third version of the project plan will be turned in. 17. User Interface Design: This deliverable will show human-computer interactions. 18. Test Plan Deliverable: The test plan describes how the tester will verify that the system works as intended. START DATE 10/23/2023 END DATE 10/29/2023 OVERALL PROGRESS 92%
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
AT RISK TASK NAME ASSIGNED TO START DATE END DATE DURATION in days % Complete STATUS Notes Stakeholder Survey Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 09/18/2023 09/21/2023 4 100% COMPLETED Requirements Management Caleb Smith and Jaleel Harris 09/18/2023 09/21/2023 4 100% COMPLETED Scope Document Caleb Smith and Scarlet Mendoza 09/18/2023 09/21/2023 4 100% COMPLETED Work Breakdown Structure Caleb Smith 09/18/2023 09/21/2023 4 100% COMPLETED Weekly Progress Report V2 Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 09/21/2023 09/24/2023 4 100% COMPLETED Team Meeting Plan Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah 09/21/2023 09/24/2023 4 100% COMPLETED
Bagunda Project Schedule Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 09/21/2023 09/24/2023 4 100% COMPLETED Project Management Plan Scarlet Mendoza 09/21/2023 09/24/2023 4 100% COMPLETED UML Diagram Caleb Smith 09/14/23 09/24/2023 10 100% COMPLETED Database UML Diagram Jaleel Harris 09/14/23 09/24/2023 10 100% COMPLETED Project Plan V2 Jaleel Harris and Scarlet Mendoza 09/28/2023 10/01/2023 4 100% COMPLETED Weekly Progress Report V3 Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 09/28/2023 10/01/2023 4 100% COMPLETED
Requirements Document Caleb Smith 9/28/2023 9/29/2023 1 100% COMPLETED Team Meeting 2 Caleb Smith, Jaleel Harris and Scarlet Mendoza 09/28/2023 09/28/2023 1 100% COMPLETED Use Case Analysis Jaleel Harris and Scarlet Mendoza 10/09/23 10/15/23 7 100% COMPLETED Weekly Progress Report V4 Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 10/12/23 10/15/23 4 100% COMPLETED Project Plan V3 Scarlet Mendoza 10/09/23 10/12/23 4 100% COMPLETED Initial Testing Round Caleb Smith, and Jaleel Harris 10/09/23 10/29/23 20 10% IN PROGRESS The database will be tested alongside the code which was previously written. This will allow the team to see any errors in the code or database and will allow the team to move forward in the project. As of October 19th the initial round of testing has been prolonged two weeks to allow the team to work on the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
database and website longer. User Interface Design Caleb Smith and Jaleel Harris 10/16/23 10/22/23 6 100% COMPLETE User Interface design is currently done. Project Plan V4 Scarlet Mendoza 10/16/23 10/22/23 6 100% COMPLETE Progress Report V5 Caleb Smith, Jaleel Harris, Scarlet Mendoza, and Deborah Bagunda 10/16/23 10/22/23 6 100% COMPLETE Done individually and turned in. Functional Test Plan Caleb Smith, Jaleel Harris, and Scarlet Mendoza 10/26/23 10/29/23 4 5% IN PROGRESS The Functional Test Plan is currently being worked on and will be turned in before or on the 29th of October. Project Plan V5 Scarlet Mendoza 10/26/23 10/26/23 1 100% COMPLETE