PROJECT PLAN V5
Pear Development Studio
Team:
Caleb Smith, Jaleel Harris,
Scarlet Mendoza, Deborah Bagunda
Instructor:
Professor Ade Thompson
Course:
CIST 2931 - Advanced Systems Project
Date:
October 29, 2023
SOFTWARE DEVELOPMENT
PROJECT PLAN
PROJECT NAME
SellBuy eCommerce
PROJECT MANAGER
Jaleel Harris
PROJECT
DELIVERABLE
During this week:
-
Test Plan Deliverable: The test plan describes how the tester will verify that the system works as intended.
-
Project Plan V5: The third version of the project plan will be an updated version of the previous plans.
-
Weekly Progress Report V6: The progress report will be done individually and will show the progress of the project.
SCOPE
STATEMENT
1.
Stakeholder Survey: This survey was done in order to investigate and research information which will affect our project.
2.
Requirement Management: This is done with the purpose of figuring out all the requirements of the project.
3.
Scope Document: The Scope Document includes a detailed description of the project, its objectives and the deliverables
which will be produced during the course of the project.
4.
Work Breakdown Structure: The WBS breaks down the work of the project into smaller sections.
5.
Weekly Progress Report Plan V1: The first version of the Weekly Progress Report Plan was completed by each team
member to view the progress made this week.
6.
Team Meeting Plan: The Team Meeting Plan is done to ensure every team member knows what their job is for that
week.
7.
Project Schedule: The Project Schedule is made based on previous documents like the Scope Document.
8.
Project Management Plan: Every week, the Project Plan will be updated.
9.
Project Plan Document V2: The second version of the project plan will be completed and turned in.
10. Functional and Nonfunctional Requirements: The requirements of the project will be discussed and written down on a
document.
11. UML Diagram: The UML diagram for the system will be worked on.
12. Database UML Diagram: The UML for the database will be worked on.
13. Weekly Progress Report V3: The individual progress report will be completed and turned in.
14. Use Case Analysis: The Use Case Analysis will include information about the users, the product, and their interactions.
15. Weekly Progress Report V4: The fourth version of the progress report will be done individually.
16. Project Plan Document V3: The updated third version of the project plan will be turned in.
17. User Interface Design: This deliverable will show human-computer interactions.
18. Test Plan Deliverable: The test plan describes how the tester will verify that the system works as intended.
START DATE
10/23/2023
END DATE
10/29/2023
OVERALL PROGRESS
92%
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
AT
RISK
TASK NAME
ASSIGNED TO
START
DATE
END
DATE
DURATION
in days
% Complete
STATUS
Notes
Stakeholder
Survey
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
09/18/2023
09/21/2023
4
100%
COMPLETED
Requirements
Management
Caleb Smith and
Jaleel Harris
09/18/2023
09/21/2023
4
100%
COMPLETED
Scope
Document
Caleb Smith and
Scarlet Mendoza
09/18/2023
09/21/2023
4
100%
COMPLETED
Work
Breakdown
Structure
Caleb Smith
09/18/2023
09/21/2023
4
100%
COMPLETED
Weekly
Progress
Report V2
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
09/21/2023
09/24/2023
4
100%
COMPLETED
Team Meeting
Plan
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
09/21/2023
09/24/2023
4
100%
COMPLETED
Bagunda
Project
Schedule
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
09/21/2023
09/24/2023
4
100%
COMPLETED
Project
Management
Plan
Scarlet Mendoza
09/21/2023
09/24/2023
4
100%
COMPLETED
UML Diagram
Caleb Smith
09/14/23
09/24/2023
10
100%
COMPLETED
Database UML
Diagram
Jaleel Harris
09/14/23
09/24/2023
10
100%
COMPLETED
Project Plan V2
Jaleel Harris and
Scarlet Mendoza
09/28/2023
10/01/2023
4
100%
COMPLETED
Weekly
Progress
Report V3
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
09/28/2023
10/01/2023
4
100%
COMPLETED
Requirements
Document
Caleb Smith
9/28/2023
9/29/2023
1
100%
COMPLETED
Team Meeting
2
Caleb Smith,
Jaleel Harris and
Scarlet Mendoza
09/28/2023
09/28/2023
1
100%
COMPLETED
Use Case
Analysis
Jaleel Harris and
Scarlet Mendoza
10/09/23
10/15/23
7
100%
COMPLETED
Weekly
Progress
Report V4
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
10/12/23
10/15/23
4
100%
COMPLETED
Project Plan V3
Scarlet Mendoza
10/09/23
10/12/23
4
100%
COMPLETED
Initial Testing
Round
Caleb Smith, and
Jaleel Harris
10/09/23
10/29/23
20
10%
IN
PROGRESS
The database will be tested
alongside the code which was
previously written. This will
allow the team to see any
errors in the code or database
and will allow the team to
move forward in the project.
As of October 19th the initial
round of testing has been
prolonged two weeks to allow
the team to work on the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
database and website longer.
User Interface
Design
Caleb Smith and
Jaleel Harris
10/16/23
10/22/23
6
100%
COMPLETE
User Interface design is
currently done.
Project Plan V4
Scarlet Mendoza
10/16/23
10/22/23
6
100%
COMPLETE
Progress
Report V5
Caleb Smith,
Jaleel Harris,
Scarlet Mendoza,
and Deborah
Bagunda
10/16/23
10/22/23
6
100%
COMPLETE
Done individually and turned
in.
Functional Test
Plan
Caleb Smith,
Jaleel Harris, and
Scarlet Mendoza
10/26/23
10/29/23
4
5%
IN
PROGRESS
The Functional Test Plan is
currently being worked on
and will be turned in before or
on the 29th of October.
Project Plan V5
Scarlet Mendoza
10/26/23
10/26/23
1
100%
COMPLETE