week 2 assignment

docx

School

Cumberland University *

*We aren’t endorsed by this school

Course

5131

Subject

Information Systems

Date

Dec 6, 2023

Type

docx

Pages

18

Uploaded by MatePuppyMaster3743

Report
What are the main differences between the two versions of the JWD Consulting case study? The differences are as follow: Firstly, the main difference between pre- initiation would be determining roles and deciding what functionality would be delivered as part of each
release, how many sprints will be required to complete a release, and how many releases of software to deliver. In the prescriptive approach, only one release of the software would be made which will be at the very end. Secondly, in prescriptive approach the planning
process includes creating a team charter, WBS, Gantt chart, and list of prioritized risks for the whole project. In agile approach, the team follows a scrum method; a preliminary scope statement is written and in place of a WBS, high-level descriptions of the work to be completed would be identified in the
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
product and sprint backlogs. Thirdly, the team would complete tasks each day in both approaches, but by using an agile approach, the team would produce several iterations of a potentially shippable product. Next, in the prescriptive approach, a brief progress report was submitted each Friday.
However, in agile approach, daily scrum meeting is held, and a sprint review was written after each sprint. Lastly, for the closing phase, in prescriptive approach, a lesson learned report is written whereas in agile approach, a sprint retrospective is written which is intended to answer
two fundamental questions; What went well during the last sprint that we should continue doing and what could we do differently to improve the product or process? Although both approaches do differ a lot, the main difference that we found was the iterations. With the agile approach, since they were able to deliver multiple versions, they
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
could accept feedback and work on it before releasing the second update. With prescriptive or waterfall approach, there was only one final product and there was no chance of re-doing or changing the product after the release. 2. When should you use a more prescriptive or agile approach?
Projects with heavy constraints, inexperienced and dispersed teams, large risks, generally clear up-front requirements, and a fairly rigid completion date are best done using a predictive approach. In contrast, projects with less rigid constraints, experienced and preferably co-located
teams, smaller risks, unclear requirements, and more flexible scheduling would be more compatible with an agile approach. What are the main differences between the two versions of the JWD Consulting case study? The differences are as follow:
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Firstly, the main difference between pre- initiation would be determining roles and deciding what functionality would be delivered as part of each release, how many sprints will be required to complete a release, and how many releases of software to deliver. In the prescriptive approach, only one
release of the software would be made which will be at the very end. Secondly, in prescriptive approach the planning process includes creating a team charter, WBS, Gantt chart, and list of prioritized risks for the whole project. In agile approach, the team follows a scrum method; a preliminary
scope statement is written and in place of a WBS, high-level descriptions of the work to be completed would be identified in the product and sprint backlogs. Thirdly, the team would complete tasks each day in both approaches, but by using an agile approach, the team would produce several
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
iterations of a potentially shippable product. Next, in the prescriptive approach, a brief progress report was submitted each Friday. However, in agile approach, daily scrum meeting is held, and a sprint review was written after each sprint. Lastly, for the closing phase, in prescriptive
approach, a lesson learned report is written whereas in agile approach, a sprint retrospective is written which is intended to answer two fundamental questions; What went well during the last sprint that we should continue doing and what could we do differently to improve the product or process?
Although both approaches do differ a lot, the main difference that we found was the iterations. With the agile approach, since they were able to deliver multiple versions, they could accept feedback and work on it before releasing the second update. With prescriptive or waterfall approach, there was only
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
one final product and there was no chance of re-doing or changing the product after the release. 2. When should you use a more prescriptive or agile approach? Projects with heavy constraints, inexperienced and dispersed teams, large risks, generally clear up-front requirements, and a fairly
rigid completion date are best done using a predictive approach. In contrast, projects with less rigid constraints, experienced and preferably co-located teams, smaller risks, unclear requirements, and more flexible scheduling would be more compatible with an agile approach. In the JWD consulting project there were five key differences between the two versions of the case. First, in the agile approach multiple releases would occur, in the perspective approach the software would be released only a single time which would be mark the
completion of the project. A second difference is that in the perspective approach a team charter, WBS, Gantt char and a list of prioritized risks for the entirety of the project is part of the planning process. However, in the agile approach a scrum method is used instead. A third difference is that using the agile approach the team would produce multiple versions of the software leading up to a launch. Fourth, using the agile approach daily meetings were held whereas in the perspective approach a brief progress note was sent at the end of each week. Overall the difference between the agile and perspective versions of the project was that the agile approach delivered multiple options and therefore could accept feedback and make adjustments as the project continued to develop. The perspective approach wielded one final product that could accept feedback, but not do anything to make changes or corrections. In the perspective approach it was more well suited because it had a clear budget and timeline with a well-defined focus and more intensive research could be done that allowed for a fuller understanding of the product. However that approach is not at all flexible and there is little room for error. In the agile approach the risks are lower and the overall project has more flexibility as updates can be made after each version release which gives JWD more control over the project as a whole. These factors produce a higher level of customer satisfaction in general because the product has received feedback. The downside to the agile approach is that the project can in theory go on forever and costs continue to rise and often exceed budget due to constant changes and updates pushing timelines to ROI further back. After reading both versions it appears JWD users would prefer an agile approach. The technological world is every changing and therefore the ability to make updates and changes as needed would be beneficial Additionally if the initial launch garnishes a lot of negative feedback there is plenty of room to make changes and improvements. The company would also be able to have the product live sooner as they could launch a rudimentary version and then take user feedback and apply it to the next version release.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help