IT 510 Module Two Homework Activity Use Microsoft Project to review the plan provided to you. The project plan is the initial draft based on the case. You will need to analyze the plan and make proper adjustments to meet the timeline requirements, as well as to ensure that resources are properly allocated. Additionally, you will add resource per hour costs so that you can include the estimate of cost for the project. Perform the following tasks and prepare a document that includes the answers to questions in the task list below: 1.
Using Microsoft Project, open the plan (Module Two Homework Project File, in the Assignment Guidelines and Rubrics section of the course). 2.
Review the different project views. You can do this by using the drop-down arrow on the Gantt Chart
icon in the top left of the project menu. Review the following project view: a)
Gantt Chart—Usage Table i.
From the Gantt Chart view, select the View tab from the top toolbar. ii.
On the View tab, select the Tables drop-down and select Usage. b) Network Diagram c)
Resource Sheet d)
Resource Usage—Summary Table 1.
Select the Resource
Usage
view from the Gantt Chart
drop-down. 2.
While you are in the Resource
Usage
view, select the View
tab from the top toolbar. 3.
On the View
tab, select the Tables
drop-down and select Summary. e) Task Sheet f) Timeline Reviewing these different views provides further insight into the project schedule. Note that the options under drop-down menus in Project will contain different
content depending on which tab you have selected on the top toolbar. For example, if you have the Task
tab selected, the Gantt Chart
dropdown will have different options than when the View
tab is selected. Similarly, the Tables
drop-down will change the view based on the specific chart being displayed. 3.
Return to the Gantt
Chart
view. Notice the total duration is 56 days, which is more than two months. a)
Ensure that Auto Schedule is selected for the project. i.
The status bar at the bottom of the screen should read, “New Tasks: Auto Scheduled.” If it does not, click on the New Tasks
:
.
.
.
text in the status bar and select Auto Scheduled
. 1.
You can also change this setting by selecting the Task
tab from the top toolbar and clicking the Auto
Schedule
icon.
b)
Change the following 14d tasks to 10d tasks: i.
Fact Find ii.
Review Existing System iii.
Create Web Page Prototype iv.
Create iOS Prototype You realized that you meant two weeks, but that is 10 days in a project and not 14 days. Notice that the total duration is now 48 days and work is 768 hours, which is very close to two months in length. 4.
From the Gantt Chart
drop-down, select the Resource Sheet
. a)
Notice that two resources are red. These resources are assigned to more work than they have hours available to work. This means they are overallocated. b)
From the Gantt Chart
drop-down, select Resource
Usage. i.
While you are in the Resource
Usage view, select the View
tab from the top toolbar. ii. On the View tab, select the Tables
drop-down and select Summary. In this view, you can see (in the grid on the right) the number of hours allocated per day for each resource. Numbers in red indicate that there is an over-allocation. c) Note that the following tasks are over-allocated: i. System Analyst 1.
Fact Find 2.
Review Existing System 3.
Review Solution Architecture 4.
Validate Prototype ii.
Project Manager 1.
Create Business Case Document 2.
Create Schedule
3.
Fact Find 4.
Review Existing System 5.
Determine Recommendation 6.
Create Executive Presentation For each of the over-allocated tasks, note the number of work hours for each day in the grid on the right. (You will need to scroll horizontally to see all days of the project.) 7.
Double-click the over-allocated tasks to get the Assignment Information
panel. 8.
On the General
tab, change the Units
from 100% to 50% and select OK. 9.
Note the change in the number of hours on the task after each change. a. Repeat this process for each of the over-allocated tasks. From the Gantt Chart
drop-down, return to the Resource Sheet view and note that the resources are no longer in red. All over-allocations have been resolved by reducing the units from 100% to 50%. 5.
Return to the Gantt Chart
. Select the View tab and, from the Tables
drop-down, select Usage
.
a)
Notice the following: i.
Duration changed from 48 to 69 days.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
ii.
Work remained the same at 768 hours. b)
Navigate to Help in Microsoft Project. i.
Search for “Duration Unit Work Formula.” ii.
Review the article titled “Change the task type for more accurate scheduling.” c)
In 2 to 3 sentences, respond to the prompt below in a Word document. Use the heading “Resource Assignments.” i.
Why did the duration change, and work remain the same when the resource units were changed from 100% to 50%? 6.
Change to the Resource Sheet. For each resource, enter the following hourly cost for the standard rate: a)
Web Developer, $35/h b)
Mobile Developer, $35/h c)
Project Manager, $50/h d)
System Analyst, $50/h 7.
Change to the Gantt Chart
view
. Select the View
tab
and, from the Tables
drop-down, select Cost. a)
In 2 to 3 sentences, respond to the prompt below in your Word document. Use the heading “Project Cost.” i.
What is your total project cost? Referencing the “Duration Unit Work Formula,” explain how changes in this formula can change your total project cost during the execution of the project plan. 8.
Change to the Project tab and select Project
Information
. Click on the Statistics…
button. Take a screenshot
of the Project Statistics
dialog box and include this as the last item in your Word document.
Resource Assignments
Why did the duration change, and work remain the same when the resource units were changed from 100% to 50%? When the resource units were changed from 100% to 50%, the Units variable in the formula decreased by half. However, the Work variable remained the same as
it is determined by the amount of work required for the task and does not change with the resource allocation.
In conclusion, the duration changed because of the decrease in resource units, while the work remained the same because it was not affected by resource allocation.
Project Cost
What is your total project cost? Referencing the “Duration Unit Work Formula,” explain how changes in this formula can change your total project cost during the execution of the project plan.
My total project cost
is $36,000. The Duration Unit Work Formula calculates the work required for a specific duration. Changes in the formula, such as the amount of work or the duration, will affect the total project cost as it directly impacts the resources and manpower needed to complete the project within the given
timeline. Therefore, any changes in the Duration Unit Work Formula will impact the project budget and may result in cost overruns or increased expenses.