CPCCBC 40
Site Address :
03 Task 6 Practical Completion Checklist ABC Building PTY LTD
DATE
Site Manager :
Check Date
Document Preparation - RBS
Certificate of Occupancy
1
Slab & Foundation Inspection Certificate
2
Frame Inspection Certificate
3
Final Inspection Certificate
4
Truss design & Certification
5
Engineer Slab Design & certification
6
Glazing certificate/s
7
Roof and Wall Insulation Certificate
8
Waterproofing Certificate
9
Contract- Stage claims x 6
10
Contract - Variations- signed & complete
11
Contract - Variations- signed & complete
12
Contract - Final Invoice 10% + Variations + GST
13
Extension of Time - noted & complete
14
Plumbing, Draining & Gas Certification- PCA
15
Electrical Certification- Energy Australia
16
6 Star Energy Certification
17
Smoke Alarm- Check locations & certification
Complete & Checked
InternaL checklist
1
Rooms- Walls & Ceiling Painting & Plaster Defects- noted and fixed
2
Rooms - Door furnture - handles.Latches & stops - complete and intact
3
Rooms- Windows- Flyscreens intact- sills & tracks clean
4
Baths, showers & toilets-Working- Dry , clean & wiped
5
Kitchen- Draws & doors working - drawers wiped & cleaned
6
Laundry - Bench & Sink - Dry wiped & clean
7
Floor tiles- Cleaned & mopped
8
Carpet or Timber flooring- Vacumed ,Clean & tidy
9
Light Fittings- Clean & Operating
10
Tapware- Clean & Operating
11
Whitegood appliances- Clean & Operating
12
Cabinetry- Kitchen , vanities, Laundry - sealed at edges
13
Garage concrete floor - clean & swept- Cracks noted
External Checklist
1
Roof tile- Installation certificate- clean , no debris
2
Gutters- Clean , no debris, no paint scratches
3
Eaves- no paint drips or defects, nails
4
External Vents- clean & operating
5
Brickwork, clean , no paint drips
6
Brickwork- AJ's sealed
7
Windows- no scratch defects or paint drips- seals intact
8
External Concrete- Clean & Swept- Cracks noted
9
Garage & external doors- clean & operating- seals in place
10
BAL- Vent seals in Place - where applicable