ACQ 2550 Module 3 Exam
docx
keyboard_arrow_up
School
Defense Acquisition University *
*We aren’t endorsed by this school
Course
2550
Subject
Industrial Engineering
Date
Jan 9, 2024
Type
docx
Pages
3
Uploaded by ChancellorLlamaMaster178
Test
-
ACQ
2550
Module
3
Exam:
Scheduling
TO1.EO1
Describe
how
a
schedule
helps
to
plan
and
execute
a
services
acquisition
program.
Question
1
of
11.
Which
of
the
following
is
a
list
of
activities
and
events
organized
by
time
and
determines
what
needs
to
be
accomplished
in
order
to
meet
program
objectives?
O
Integrated
Master
Schedule
O
Milestone
plan
®
Program
plan
O
Acquisition
plan
([
Mark
for
follow
up
TO3.EO3
Interpret
Gantt
chart
symbols
and
describe
the
current
schedule
status
as
it
relates
to
the
Question
2
of
11.
On
a
Gantt
chart,
every
task
has
two
bars,
one
for
baseline
and
one
for
status.
True
False
®
O
[
Mark
for
follow
up
TO3.EO4
Identify
the
types
of
task
relationships
and
critical
path
in
a
simple
Precedence
Diagram
Me
Question
3
of
11.
Which
of
the
following
information
is
typically
included
on
a
Precedence
Diagramming
Method
(PDM)
activity
node?
Select
three
that
apply.
Float
times
Early
start
and
finish
dates
Duration
J
Resource
constraints
([
Mark
for
follow
up
TO1.EO2
Select
the
appropriate
scheduling
tool
to
support
a
services
acquisition
program.
Question
4
of 11.
Which
of
the
following
are
considerations
when
determining
scheduling
tool
needs?
Select
three
that
apply.
The
complexity
of
the
scheduling
issues
(J
If
one
license can
be
used
freely
by
everyone
(i.e.,
government
or
contractor)
on
the
team
The
types
of
outputs
needed,
such
as
network
or
Gantt
charts
Whether
or
not
it
is
compatible
with
other
products
([
Mark
for
follow
up
TO3.EO2
Identify
examples
of
speci
ic
schedule
types,
and
list
two
program
management
uses
for
each.
Question
5
of
11.
The
Summary
Schedule
graphically
displays
the
required
events
and
milestones
to
complete
the
program
or
project.
True
False
®
O
[
Mark
for
follow
up
TO4.EO2
Determine
at
least
one
potential
corrective
action
for
a
specific
resource-constrained
sched
Question
6
of
11.
Which
corrective
action
for
resource-constrained
schedules
calls
for
you
to
change
the
scope
of
the
program,
hopefully
alleviating
resource
constraints?
O
Substituting
a
resource
O
Adjusting
the
schedule
O
Adding
a
resource
@
Reducing
the
scope
([
Mark
for
follow
up
TO4.EO3
Determine
at
least
one
potential
corrective
action
for
a
specific
time-constrained
schedule
Question
7
of
11.
Conducting
tasks
simultaneously
and
accepting
a
longer
project
length
are
potential
corrective
actions
for
a
resource-constrained
schedule.
True
False
®
O
([
Mark
for
follow
up
TO2.EO2
Describe
how
an
Integrated
Master
Plan
and
an
Integrated
Master
Schedule
helps
to
manage
a
s
Question
8
of 11.
The
Integrated
Master
Plan
(IMP)
and
Integrated
Master
Schedule
(IMS)
can
help
the
Program
Manager
(PM)/Functional
Services
Manager
(FSM)
scope
the
contractual
effort
and
.
Fill
in
the
blank.
O
Allocate
the
resources
necessary
to
complete
each
task
®
Provide
a
realistic
basis
for
initial
cost
and
schedule
estimates
O
Be
used
as
a
metric
to
evaluate
contractor
proposals
O
Beused
by
contractors
in
their
proposals
so
they
don't
need
to
create
new
ones
()
Mark
for
follow
up
TO2.EO1
Distinguish
between
an
Integrated
Master
Plan
(IMP)
and
Integrated
Master
Schedule
(IMS).
Question
9
of
11.
The
Integrated
Master
Plan
(IMP)
is
directly
traceable
to
the
Integrated
Master
Schedule
(IMS)
and
other
documentation
that
shows
the
detailed
tasks
necessary
to
accomplish
the
work
effort.
True
False
®
O
[
Mark
for
follow
up
TO3.EO1
Describe
the
six-step
process
to
prepare
and
manage
program
schedules.(
Question
10 of
11.
It
is
important
for
planners
to
document
assumptions
and
constraints
when
estimating
the
length
of
time
required
to
accomplish
a
task.
If
an
assumption
changes
or
a
constraint
is
removed,
the
length
of
time
will
need
to
be
recalculated.
True
False
®
O
([
Mark
for
follow
up
TO4.EO1
Describe
the
differences
between
a
resource-constrained
schedule
and
a
time-constrained
sche
Question
11
of 11.
You have
been
tasked
with
acquiring
a
service
to
take
over
the
cooking
duties
for
the
on-base
dining
facility.
Every
proposal
submitted
claims
that
it
will
cost
at
least
$3.5
million dollars
to
do
the
work
in
the
requested
amount
of
time.
However,
only
$2.5
million
dollars
has
been
allocated
for
this
services
acquisition.
What
type
of
constraint
are
you
dealing
with
here?
©
Sschedule
constraint
@®
Cost
constraint
O
Time
constraint
O
organizational
constraint
(J
Mark
for
follow
up
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help