Pert Problem

docx

School

Bowling Green State University *

*We aren’t endorsed by this school

Course

MSA5160

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

docx

Pages

2

Uploaded by GabrielNaimy1992

Report
A firm is planning a project for the development of a new product. Assume the network of activities and data presented the excel document posted below. 1. Using the PERT method (critical path method with three activity time estimates), calculate the expected time and standard deviation of the time for each activity. (If you don’t know the critical path method or the PERT method, you may search online or read a regular textbook in project management or operations management.) 2. Based on the expected time for each activity, using the critical path method, determine the project duration and critical path. 3. Using the PERT method, estimate the probability of the project to be completed within 36 weeks. 4. Using Monte Carlo Simulation, estimate the probability of the project to be completed within 36 weeks. Note that the time for each activity can be assumed to follow a normal distribution with the mean and standard deviation calculated in 1). You can use Excel or any other software package to develop a Monte Carlo simulation model. You may generate 1,000 simulation replications. For each replication, the simulation model should determine the project completion time based on the network of activities. 5. Are the results derived from the PERT method in 3) and from the Monte Carlo Simulation in 4) the same? Discuss why or why not. Activity Immediate Predecessor Minimum Time (Weeks) Most Likely Time (Weeks) Maximum Time (Weeks) A 12.3 14.2 19.7 B A 5.5 7.7 11.2 C A 3.7 6 11.5 D B 1.8 3.9 6.8 E C 1.4 4.1 6.6 F B, C 1 2.4 5.5 G D, E, F 5 5 5 For each activity, calculate the expected time (TE) using the formula: TE = (a + 4m + b) / 6, where a is the minimum time, m is the most likely time, and b is the maximum time. Calculate the standard deviation (SD) using the formula: SD = (b - a) / 6. Apply these formulas for each activity A to G •Identify the critical path, which is the longest path through the network. •Calculate the project duration by summing the expected times along the critical path.
Estimate the probability of the project completion within a given time using the normal distribution. Calculate Z-scores for the desired time (e.g., 36 weeks) using the formula: Z = (X - TE) / SD, where X is the desired time, TE is the expected time, and SD is the standard deviation. Use a standard normal distribution table to find the probability. Use a software tool like Excel to simulate the project completion time. Generate random numbers for each activity based on the normal distribution with the calculated mean and standard deviation. Sum the times along the paths to get the project completion time. Repeat this process for a large number of replications (e.g., 1,000 times) to estimate the probability of completing the project within 36 weeks. Results from the PERT method and Monte Carlo Simulation may not be exactly the same due to the inherent assumptions and simplifications in each method. PERT assumes a beta distribution for activity times, while Monte Carlo Simulation uses a more flexible approach based on random sampling. Differences could also arise from how uncertainties are modeled and the underlying assumptions about the distribution of activity times. Any disparities could be due to the stochastic nature of the simulation and the way uncertainties are represented. It's essential to interpret the results with an understanding of the assumptions and limitations of each method. The expected project duration is 35.1 weeks. The probability of the project being completed within 36 weeks is 60.2%.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help