MGT 382-HW3-

docx

School

Mercer University *

*We aren’t endorsed by this school

Course

348

Subject

Industrial Engineering

Date

Dec 6, 2023

Type

docx

Pages

3

Uploaded by YC5040

Report
Problem 1) (25 points) Joe Henry’s machine shop uses 2,800 brackets during the course of a year. These brackets are purchased from a supplier 90 miles away. The following information is known about the brackets: Annual Demand 2800 Holding Cost per bracket per year $2 Order Cost per order $20 Lead time 2 Working days per year 270 a) Given the above information, what would be the economic order quantity (EOQ)? Using the information given in the question, we can plug in the values and calculate the EOQ as follows: EOQ=22×2800×20 EOQ=56000 EOQ=236.64 b) Given the EOQ, what would be the average inventory? What would be the annual inventory holding cost? c) Given the EOQ, how many orders would be made each year? -13 What would be the annual order cost? Annual order cost = 20 * 20 = $400 Therefore, the number of orders made each year is 20 orders and the annual order cost is $400 . d) Given the EOQ, what is the total annual cost of managing the inventory? Total annual cost = (2800/140)*20 + (140/2)*2 = $400 + $140 = $540 Therefore, the total annual cost of managing the inventory is $540 . e) What is the time between orders? Time between orders = 270 / (2800/140) = 13.5 days Therefore, the time between orders is 13.5 days . . f) What is the reorder point (ROP)?
where Safety stock is the amount of inventory held to mitigate the risk of stockouts. Since the problem does not provide any information about the safety stock, we cannot calculate the reorder point Problem 2) (25 points) Emarpy Appliance is a company that produces all kinds of major appliances. Bud Banis, the president of Emarpy, is concerned about the production policy for the company’s bestselling refrigerator. The annual demand has been about 9,000 units each year, and this demand has been constant throughout the year. The production capacity is 220 units per day. Each time production starts, it costs the company $150 to move materials into place, reset the assembly line, and clean the equipment. The holding cost of a refrigerator is $70 per year. The current production plan calls for 500 refrigerators to be produced in each production run. Assume there are 250 working days per year. a) What is the daily demand of this product? 36 units b) If the company were to continue to produce 500 units each time production starts, how many days would production continue? 18days c) Under the current policy, how many production runs per year would be required? What would the annual setup cost be?13,500 d) If the current policy continues, how many refrigerators would be in inventory when production stops? 1000. What would the average inventory level be? 200 e) If the company produces 500 refrigerators at a time, what would the total annual setup cost and holding cost be? 63,000 f) If Bud Banis wants to minimize the total annual inventory cost, how many refrigerators should be produced in each production run? How much would this save the company in inventory costs compared to the current policy of producing 500 in each production run? 180 refrigerators/saving 3,150 Problem 3) (25 points) Emery Pharmaceutical uses an unstable chemical compound that must be kept in an environment where both temperature and humidity can be controlled. Emery uses 800 pounds per month of the chemical, estimates the holding cost to be 35% of the purchase price (because of spoilage), and estimates order costs to be $40 per order. The cost schedules of two suppliers are as follows: Vendor 1 Vendor 2 Quantity Price/LB Quantity Price/LB 1-499 $17 1-399 $17.00 500-999 16.65 400-799 16.50 1000+ 16.35 800-1199 16 1200+ 15.50 a) What quantity should be ordered for each vendor, and which vendor should be used?
For Vendor 1 is 333 units and for Vendor 2 is 332 Units/ Therefore, the best option is to place the order with Vendor 2 for an order size of 1,200 units . b) What is the total cost for the most economic order size? The total cost for the most economic order size is $7,880 . This is calculated as follows: Total cost = (D/Q)*S + (Q/2)*H For Vendor 2: D = 800 pounds per month Q = 1,200 units S = $40 per order H = 35% of $16.00 per pound = $5.60 per pound per year Total cost = (800*12/1,200)*40 + (1,200/2)*0.35*16 = $320 + $3,360 = $3,680 Total cost per year = $3,680*12 = $44,160 c) What factor(s) can be considered besides total cost? Other factors that can be considered besides total cost include the quality of the chemical compound, the reliability of the supplier, and the lead time for delivery.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help