C I V I L A N D E N V I R O N M E N T A L E N G I N E E R I N G D E P A R T M E N T
C O N S T R U C T I O N E N G I N E E R I N G A N D M A N A G E M E N T
C O N S T R U C T I O N E N G I N E E R I N G A N D M A N A G E M E N T
C I V I L A N D E N V I R O N M E N T A L E N G I N E E R I N G D E P A R T M E N T
V
I R G I N I A
P
O L Y T E C H N I C
I
N S T I T U T E A N D
S
T A T E
U
N I V E R S I T Y
C
EE
-3014
C
ONSTRUCTION
M
ANAGEMENT
A
SSIGNMENT
8
T
HE
M
OUNT
H
OKIE
P
ROJECT
J
OB
C
OSTING
Notes:
•
This is a
GROUP
assignment. You can only
discuss concepts
with other groups.
No other discussions
are allowed. DO NOT COPY answers from any sources such as Internet or Past Assignments.
•
This assignment is worth
100 points.
•
If you have a problem or question after reading the assignment, email your instructor or TA.
•
Assignment is to be turned in as a PDF
CEE-3014 Construction Management
Assignment 8
CEE-3014 Construction Management
Page
2
of
4
C
EE
-3014
C
ONSTRUCTION
M
ANAGEMENT
A
SSIGNMENT
8
–
T
HE
M
OUNT
H
OKIE
P
ROJECT
J
OB COSTING
Setting:
In the afternoon of the 27
th
workday for Site Pro on the job of Mount Hokie, Tim Timer just finished
his work on the new schedule. The schedule shows that the installation of the storm water system will be
delayed.
He gave the schedule to Peter, who was worried about the possible higher cost of completion. He
called his old high school friend, Cassandra Costa, who works for an Architect/Engineering firm in Ohio.
The telephone call went like this:
Peter
:
Hi Cassy, it’s Peter. I
have a little bit of a problem on one of our
jobs and…
Cassy
: …and I’m supposed to help you out again.
Peter
: Yes, please!
Cassy
: I guess it has something to do with costs, right?
Peter
: Right.
Cassy
: Peter, why don't get yourself a book about construction cost control? Or even better, try to take a
course in this. You can't turn to me all the time. I have a job to do here myself.
Peter: Cassy, how about this? I'll promise you that I will get knowledgeable with this construction cost
stuff, if you can do me this last favor. Please!
Cassy
: That does not sound like a good deal, but I will help you out this LAST time.
Peter
: Thank you so much!
Peter sent Cassandra a fax with the old cost estimate and the three schedules from Tim Timer. He also
added the following information to the fax:
"The price of the bedding material actually turned out to be $19/LCY. As far as the placement and
compaction of the bedding material is concerned, the price per LCY for each of them is $0.10 less than
the estimate. The excavation is $0.74/LCY. That is indeed very close to our estimate. The price per LF for
laying and jointing the pipes went up by $0.10. All other costs are as estimated."
CEE-3014 Construction Management
Assignment 8
CEE-3014 Construction Management
Page
3
of
4
Additional data from Peter’s f
ax
Table 9.1
–
Budgeted Cost
Item
Unit Cost
Unit
Quantity (units)
Total Cost
Pipe Material
$45.00
LF
2,000
$90,000
Bedding Material
$17.00
LCY
361
$6,137
Excavation
$0.79
LCY
3919
$3,096
Place Bed Material
$3.49
LCY
361
$1,260
Compact Bed Material
$1.46
LCY
361
$527
Lay and Joint Pipe
$11.27
LF
2000
$22,540
Backfill
$1.23
LCY
4040
$4,969
Compaction
$1.61
LCY
4040
$6,504
Overhead
$62.50
HR
368
$23,000
Table 9.2
–
Quantity Summary
Item
Quantity
Unit
Pipe Material
2,000
LF
Bedding Material
361
LCY
Excavation
3,919
LCY
Place Bed Material
361
LCY
Compact Bed Material
361
LCY
Lay and Joint Pipe
2,000
LF
Backfill
4,040
LCY
Compaction
4,040
LCY
Overhead
368
HR
Table 9.3
–
Actual Work Completed at EOD 27
(from A7 schedule with both delays)
Table 9.4
–
Scheduled Work Completed at EOD 27
(from A7 original schedule)
Item
Quantity
Unit
Pipe Material
2,000
LF
Bedding Material
361
LCY
Excavation
3,919
LCY
Place Bed Material
361
LCY
Compact Bed Material
361
LCY
Lay and Joint Pipe
1,000
LF
Backfill
0
LCY
Compaction
0
LCY
Overhead
216
HR
Item
Quantity
Unit
Pipe Material
1,500
LF
Bedding Material
361
LCY
Excavation
3,919
LCY
Place Bed Material
361
LCY
Compact Bed Material
361
LCY
Lay and Joint Pipe
800
LF
Backfill
570
LCY
Compaction
456
LCY
Overhead
216
HR
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
CEE-3014 Construction Management
Assignment 8
CEE-3014 Construction Management
Page
4
of
4
Assignment 8
Imagine you are cost expert, Cassandra Costa. Use the data provided in the handout and produce an
estimate of the cost of the work at completion. Calculate the following as the basis of your report:
1.
The scheduled work in % completed by the end of workday 27 for each activity/item in the cost
estimate, and thus the budgeted cost of work scheduled based on Tim Timer’s original schedule.
2.
The actual work in % completed by that time for the same activities/items and thus the budgeted cost
of work performed.
3.
The actual cost of work performed based on the estimate updates that Peter tells Cassandra.
4. The cost performance index as well as the schedule performance index for each of the
activities/items by the end of the 27
th
workday.
Prepare a memo summarizing the results from the report and then attach this report to the memo.