CHANGE REQUEST
Project Title:
Home Kitchen Renovation
Date Prepared:
12/06/2023
Requestor:
Project Manager
Category:
Detailed Description of Proposed Change
After carefully looking at supply issue, we propose there will be a 2-month delay in the completion
of the kitchen renovation to allow the current supplier to deliver the necessary materials for the
project. We are aware that the delay will also have a ripple effect on other aspects of the project,
such as scheduling and subcontractor availability, but this is the most cost effect option.
Justification for Proposed Change
There is a cost variance of 5% to 10% for this project and paying a premium of 25% will dent the
budget and put a major strain on the stakeholder budget expectations.
Impacts of Change
Scope
Description: There is no impact on the scope of the project
Quality
Description: There will be no impact on quality as we will be working with a known supplier, and we can
assure quality materials will be delivered.
Scope
Quality
Requirements
Cost
Schedule
Documents
Increase
Decrease
Modify
Increase
Decrease
Modify
Requirements
Description: The requirement is not changing; it remains the same. Hence why we wish to stick with the
same supplier.
Cost
Description: There will be no impact on cost, since we are using same supplier as intended.
Schedule
Description: There will be a 2 month increase in timeline, to allow required materials to be delivered.
Stakeholder Impact
Description: There will be some impact on the stakeholder. The change in schedule will disrupt plans and use
of the renovated space.
Project Documents
Schedule Baseline
Project charter
Assumption log
Comments
The schedule is required to be updated to reflect the delivery extension, as well the assumption log
needs to be updated.
The client need to be briefed adequately and a close monitoring of the supplier must be carried
out, to avoid further delays.
Increase
Decrease
Modify
Increase
Decrease
Modify
Increase
Decrease
Modify
High Risk
Low Risk
Medium Risk
Disposition:
Justification
It is the most feasible option that will keep the cost baseline from crossing the set cost variance for
the project.
Approve
Defer
Reject