OMIS 3750 - CASE 2

pdf

School

York University *

*We aren’t endorsed by this school

Course

3750

Subject

Communications

Date

Feb 20, 2024

Type

pdf

Pages

8

Uploaded by GrandWillpowerTapir32

Report
Case 2 Analysis: The New York City Department of Parks and Recreation OMIS 3750 A
The New York City Department of Parks and Recreation’s (DPR) poor oversight has led to a history of over-budget capital expenditures and delayed deadlines. The following analysis showcases the existence of the planning fallacy at DPR. Budget Analysis The compiled data was first used to calculate the dollar variance of each project using: $ Actual - $ Budgeted = $ Variance. This calculation highlighted the amount each project went over or under budget in dollar amount. Similarly, the percentage variance was calculated using: Actual/Budgeted - 1 = % Variance. These two values were then averaged to understand the variance in dollars and percentages (Schmidt, 2022). Furthermore, an understanding of the dispersion of the data was required through the standard deviation, which was calculated using excel (=STDEV). The findings presented in Appendix 1 reveal an average dollar variance of $259,436.72, corresponding to a percentage variance of 43.52%. Further analysis of the data brings attention to a notable standard deviation of $702,014.89. This indicates a considerable dispersion in the variance of projects highlighted a negative variance between registered project budgets and actual expenditure. Deadline Analysis From the analysis of deadlines conducted, it was found that NYC DPR has an average delay of 78.2 days in completing their projects. This was calculated by subtracting the scheduled completion date from the final inspection date. From there, the average in days projects from the NYC DPR were late were found, along with standard deviation, using excel (=STDEV). A standard deviation of 190.6 days signals a significant amount of variability in the project completion times (see Appendix 3). Then able the normal distribution for the difference in days late was calculated and graphed along a normal curve (see Appendix 3) to show the variance in project completion times. Appendix 3 also highlights the inconsistency of project outcome times.
Next, using an analysis of the count of project designs delayed, early, and exactly on time (Appendix 5) showed 70% of the time designs were late, 20% were early, and 11% of the time they were completed exactly as projected (Appendix 6). This showed that only about 1 in 10 project designs were completed within the time frame suggested regarding the design phase. Other data analyzed was scheduled completion compared to actual completion of the full project. According to the results, 61.5% of the time projects were late, 32% were early and about 6% exactly on time (Appendix 6). Recommendations Enhance Budget Estimation Accuracy The variance between the departments budget projections and actual expenditures highlights errors in their current budget estimation process. A thorough review involving project managers, financial experts and relevant stakeholders should be prioritised to understand whether a top-down estimate or bottom-up estimate method should be used. Top-down estimation can provide a quick initial estimate based on past projects, allowing for rapid decision making, making it fundamental for initial project planning (Dobre, 2023). As the project progresses, a more detailed account of budgetary requirements can be estimated for tasks and project phases using the bottom-up approach. The department must focus on regularly updating estimates based on actual performance. This allows the project to be budgeted on the bases of expertise, provided by professionals with past experience in the project task (Dobre, 2023). Scheduling With an average of 78.2 days over schedule, a more rigorous scheduling plan could help the NYC DPR improve its cost and deadline accuracy since they have over 1700 city parks and facilities to maintain. To address scheduling problems, the DPR needs to identify whether a project is time-constrained or resource-constrained. If time-constrained, they can
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
use resource smoothing to reduce peak demand for resources and minimize fluctuations in resource demand (Dobre, 2023). If resource-constrained, the DPR can use the Parallel Method to apply heuristics which prioritize which activities are allocated resources and which are delayed (Dobre, 2023). The heuristics priority is; 1. minimum slack, 2. least duration, 3. lowest activity identification number (Dobre, 2023). In any period when two or more activities require the same resource, the priority rules are applied. From there, the DPR can create a proper resource schedule, assign work appropriately and use the WBS to create a time-phased budget baseline. Risk management Risk management is defined as recognizing and managing potential and unexpected circumstances that may occur once the project begins (Dobre, 2023). In order to improve project costs and meet deadlines, risk should be identified and assessed. A risk response needs to be developed to decide if risk needs to be mitigated, avoided, transferred, escalated, or retained (Dobre, 2023). An essential aspect is contingency planning. Without a contingency plan, a manager may delay decisions or accept the first proposed solution due to panic and being forced to make a decision under pressure (Dobre, 2023). Communication Although not much is mentioned on communication in the case, the author of the case explains on a podcast the importance of efficient communication procedures (Dubner 2018). For better project control, communication channels need to be streamlined. Some suggestions to implement this include implementing software that allows for easy regularly scheduled communication, both internally and externally (Forbes 2021). Additionally, the DPR can schedule regular meetings to discuss project progress and to realign deadlines if need be. Communication can look different based on each channel, but it is important to make it as efficient as possible to ensure success at the NYC DPR.
References : Dobre, M. (2023). Lecture 7: Scheduling Resources and Costs [PowerPoint slides] Dobre, M. (2023). Lecture 5: Managing Risk and PERT [PowerPoint slides] Dobre, M. (2023). Lecture 3: Estimating Time and Costs [PowerPoint slides] Dubner, Stephen J. (Host). (2018, March 7). Here's Why All Your Projects Are Always Late - and What to Do About It [Audio podcast]. Retrieved from https://freakonomics.com/podcast/heres-why-all-your-projects-are-always-late- and-what-to-do-about-it/ Forbes Magazine. (2021, August 2). 11 Ways Communications teams can prepare for long-lead deadlines. Forbes. https://www.forbes.com/sites/forbesagencycouncil/2021/08/02/11-ways-comm unications-teams-can-prepare-for-long-lead-deadlines/ Khan Academy. (n.d.). Standard deviation: Calculating step by step (article) . Khan Academy. https://www.khanacademy.org/math/statistics-probability/summarizi ng-quantitative-data/variance-standard-deviation-population/a/calculating-stan dard-deviation-step-by-step Schmidt, J. (Ed.). (2022, October 31). Budget to actual variance analysis . Wall Street Prep. https://www.wallstreetprep.com/knowledge/budget-actual-variance-analy sis-fpa/#comments
Appendices: Appendix 1: Results Table - Budget Estimations Average Variance ($) Average Variance (%) Standard Deviation $ 259,436.72 43.52% $ 702,014.89 Appendix 2: Data Calculation - Budget Estimation Appendix 3: Results Table - Deadline Estimations Average Days Late Variance Standard Deviation 78.2 36,324.3 190.6
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Appendix 4: Data Analysis of Deadline Estimation
Appendix 5: Count of late, early and on time projects Design Final Project Projects Late 1256 1101 Projects Early 343 576 Project Exactly on Time 191 113 Appendix 6: Percentage of late, early and on time projects Percentage Design Final Project Projects Late 70.16% 61.51% Projects Early 19.16% 32.18% Project Exactly on Time 10.67% 6.31%