Two Reversing Differences, Future Taxable and Deductible Amounts, No Beginning Deferred
It is estimated that the project will be completed over a three-year period starting in June 2023. By its first fiscal year end, the accounts related to the contract had the following balances:
Accounts Receivable
Contract Asset/Liability (net of billings to date of $400,000)
Revenue from Long-Term Contracts
Construction Expenses
The accounts related to the equipment that Sayaka purchased to construct the road had the following
Equipment
Accumulated Depreciation—Equipment
Undepreciated Capital Cost
Sayaka’s tax rate is 25% for 2023 and subsequent years. Income before income tax for the year ended
Required:
a) Calculate the deferred tax asset or liability balances at December 31, 2023.
Stmt of Fin. Pos. Account
Tax Base
Tax Rate
PP&E
$980,000
$930,000
$50,000
25%
$ 12,500 0
Contract Asset/Liability*
(50,000)
100,000 (150,000)
25%
(37,500)
Deferred tax liability, December 31, 2023
(25,000)
Deferred tax liability before adjustment
0
Incr. in deferred tax liability, and deferred tax expense for 2023
$(25,000)
*For the completed-contract method, the construction asset/liability account reports only con
costs excluding any gross profit recognized under the percentage-of-completion method, net o
Completed contract is used for income tax returns. $100,000 - $500,000 + $350,000 = ($50,00
b) Calculate taxable income and income tax payable for 2023.
Accounting income
Reversing differences:
Sayaka Tar & Gravel Ltd.
operates a road construction business. In its first year of operations, the com
Sayaka uses the percentage-of-completion method
of recognizing revenue
on its long-term constructi
For tax purposes, and in order to postpone the tax on such revenue for as long as possible, Sayaka use
Carrying Amount
(Taxable) Temperory Difference
Deferred Tax Asset (Liability)
Property, plant, and equipment:
Depreciation expense ($1,100,000 - $930,000)
170,000 Capital cost allowance ($1,100,000 - $980,000)
(120,000)
Contract Asset/Liability:
Gross profit – Percentage completion ($500,000 – $350,000)
(150,000)
Gross profit – Completed contract method
0
Taxable income
Current income taxes at 25%
95,000 * 25%
c) Prepare the journal entries to record income taxes for 2023.
Debit
Credit
Current Tax Expense
23,750 Income Tax Payable
23,750 To record current tax expense.
Debit
Credit
Deferred Tax Expense
25,000 Deferred Tax Liability
25,000 To record deferred tax expense.
d) Prepare the income statement for 2023, beginning with the line “Income before income tax.”
Comparative Income Statement(Partial)
For the Year Ended Dec 31
2023
Income before Income Tax
$ 195,000 Income Tax Expense-Current
23,750 Income Tax Expense-Deferred
25,000 - 48,750 Net Income / (Loss)
$ 146,250 e) Provide the SFP presentation for any resulting deferred tax balance sheet accounts at Decem
Sayaka Tar & Gravel Ltd.
Statement of Financial Position (Partial)
December 31
2023
Long-Term Liabilities
Deferred Tax Liability
$ 25,000
IFRS require that all deferred tax assets and liabilities bereported as non-current items on a c
f) Repeat the balance sheet presentation in part (e) assuming Sayaka follows ASPE
Sayaka Tar & Gravel Ltd.
(Partial) Balance Sheet
December 31
2023
Non-current assets
Future Tax Asset
$ 12,500 Current liabilities
Future tax liability
37,500
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
d Taxes, One Tax Rate
$320,000
100,000
500,000
350,000
g balances at the end of the first fiscal year ended December 31, 2023, for accounting and tax purp
$1,100,000
170,000
980,000
December 31, 2023, was $195,000. Sayaka reports under IFRS.
For ASPE Curr/LT
LT
Carrying Amount = $1,100,000 - $170,000 = $93
C
nstruction
of billings.
00)
195,000 mpany won a contract to build a road for the municipality of Cochrane West.
tion contracts.
es the completed-contract method
allowed by the CRA.
50,000 (150,000)
$ 95,000 $ 23,750 .”
mber 31, 2023. Be specific about the classification.
classified SFP
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
poses:
30,000
Related Documents
Related Questions
GinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows:
2021. 2022
Partial billing on contract 1,000,000. 4,200,000
Accounts receivable 1,000,000 3,000,000
Construction cost 1,050,000 1,920,000
Construction in progress 1,220,000 3,640,000
What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively?
2021 2022
A.220,000. 2,280,000
B.170,000. 500,000
C.220,000. 1,000,000
D.170,000. 1,280,000
arrow_forward
Ind
arrow_forward
Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of
$4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the
construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
Estimated loss.
2023
*$2,928,960+ $1,647,540
$1,017,000
3,051,000
968,000
817,000
The revised estimates for the bridge contract are as follows.
2024
$2,928,960
1,647,540
2,418,000
1,897,000
2025
$4,576,500
1,134,000
0
1,806,000
2023 Original Estimates 2024 Revised Estimates
$4,520,000
$4,520,000
4,068,000
4,576,500*
$452,000
$(56,500)
Under the percentage-of-completion
method, how would Sunland record
the long-term contract revenues,
expenses, and losses in 2024.
Please show…
arrow_forward
Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an
estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The
following data pertain to the construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
2023
Estimated loss
$1,017,000
3,05 1,000
968,000
The revised estimates for the bridge contract are as follows.
817,000
4,068,000
2024
$2,928,960
$452,000
1,647,540
2,418,000
1,897,000
2025
$4,576,500
2023 Original Estimates 2024 Revised Estimates
$4,520,000
$4,520,000
1,134,000
1,806,000
0
4,576,500*
$(56,500)
arrow_forward
road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs
incurred).
Cost incurred during the year.
Estimated costs to complete as of year-end
2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash,…
arrow_forward
Blossom Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.3 million.
Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract:
Costs incurred during the year
Estimated costs to complete
Revenue
Expenses
Gross Profit
Calculate the gross profit to be recognized each year using the completed-contract method.
$
2022
$661,000
$822,000
1,519,000 705,000
2023
2022
2024
$685,900
0
2023
$
2024
arrow_forward
Current Attempt in Progress
In 2025, Carla Vista Construction Corp. began construction work under a 3-year contract. The contract price was $1,100,000. Carla
Vista uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based
on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating
to this contract at December 31, 2025, are shown below.
Accounts receivable
Construction in process
Balance Sheet
Less: Billings
Costs and recognized profit in excess of billings
Income Statement
$64,000
62,400
Income (before tax) on the contract recognized in 2025
Portion of contract billings collected
How much cash was collected in 2025 on this contract?
$17.400
$16,640
1,600
arrow_forward
Sandhill Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.8 million.
Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract:
Costs incurred during the year
Estimated costs to complete
Revenue
Expenses
$
Gross Profit $
2022
2022
$637,000
1,489,000
$844,000
Calculate the gross profit to be recognized each year using the completed-contract method.
2023
$
$
713,000
2024
$715,900
2023
0
$
$
2024
SUPPORT
arrow_forward
Assume that Ivanhoe Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of
$4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the
construction period. Assume that progress billings are non-refundable.
Costs to date (12/31)
Estimated costs to complete (12/31)
Progress billings during the year
Cash collected during the year
Contract price
Estimated total cost
Estimated gross profit
Estimated loss
2023
$1,035,000
3,105,000
*$2,980,800+$1,676,700
955,000
788,000
2025
$2,980,800 $4,657,500
1,676,700
2024
The revised estimates for the bridge contract are as follows.
2,443,000
1,801,000
2023 Original Estimates 2024 Revised Estimates
$4,600,000
$4,600,000
4,140,000
4,657.500*
$460,000
1,202,000
2,011,000
0
$(57,500)
arrow_forward
In 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):
Accounts receivable, 12/31/2021 (from construction progress billings)
$
37.5
Actual construction costs incurred in 2021
$
135
Cash collected on project during 2021
$
105
Construction in progress, 12/31/2021
$
207
Estimated percentage of completion during 2021
60
%
How much cash remains to be collected by CCC on the project?
arrow_forward
The total estimated cost is
arrow_forward
In 2021, Montana Corp. entered into a contract to begin work on a two-year project. Montana recognizes revenue over time
according to percentage of completion for this contract, and provides the following information (dollars in millions):
Accounts receivable, 12/31/2021 (from construction progress billings) $37.5
$140
Actual construction costs incurred in 2021
Cash collected on project during 2021
$105
Construction in progress, 12/31/2021
$210
Estimated percentage of completion during 2021
Selected Amounts
O $70,000,000
What is the amount of gross profit on the project recognized by Montana during 2021?
O $60,000,000
$35,000,000
O $105,000,000
50 %
arrow_forward
snju
arrow_forward
Record the construction costs, progress billings, cash collections and gross profit (loss) for 2024, 2025 and 2026.
arrow_forward
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Problem 6-10 (Algo) Part 4
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Costs incurred during the year
Estimated costs to complete as of year-end
Revenue
Gross profit (loss)
S
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs
incurred and costs to complete information.
2024
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.
Answer is not complete.
2024
$ 2,184,000
5,616,000
2,120,000
1,860,000
2,800,000
2025
2025
$ 3,510,000…
arrow_forward
Domestic
arrow_forward
In 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $1,090,000. Sunland
uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the
proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this
contract at December 31, 2025, are shown below.
Balance Sheet
Accounts receivable
Construction in process
Less: Billings
Costs and recognized profit in excess of billings
Income Statement
$16,600
$62,500
58,000
4,500
Income (before tax) on the contract recognized in 2025
(a)
Your answer is correct.
How much cash was collected in 2025 on this contract?
(b)
Portion of contract billings collected $
eTextbook and Media
* Your answer is incorrect.
$20,000
41400
What was the initial estimated total income before tax on this contract?
Income before tax on this contract
$
4500
Attempts: 2 of 15 used
arrow_forward
In 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):
Accounts receivable, 12/31/2024 (from construction progress billings)
$ 37.5
Actual construction costs incurred in 2024
$ 135
Cash collected on project during 2024
$ 105
Construction in progress, 12/31/2024
$ 207
Estimated percentage of completion during 2024
60%
What are CCC's estimated remaining construction costs on the project at the end of 2024?
arrow_forward
H
arrow_forward
At the beginning of 2021, Florida Road Construction entered into a contract to build a road for the government. Construction will take four
years. The following information as of December 31, 2021 is available:
Revenue according to contract
10,000,000
Total expected cost
8,000,000
Cost incurred during 2021
1,200,000
Cost incurred during 2022
2,400,000
Cost incurred during 2023
Cost incurred during 2024
1,600,000
2,800,000
Compute for the reported Gross Profit of Florida using:
Year
2021
2022
2023
2024
Completed Contract Method
Zero Profit Method
Percentage of Completion Method
arrow_forward
es
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2026. Information related to the contract is as follows:
2024
$ 3,471,000
5,429,000
2,900,000
2,700,000
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time.
Cost incurred during the year
Estimated costs to complete as of year-end
2025
$ 4,005,000
1,424,000
4,576,000
4,500,000
Cost incurred during the year
Estimated costs to complete as of year-end
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs
incurred).
2024
$ 2,490,000
5,690,000
2-b.…
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you

Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Related Questions
- GinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows: 2021. 2022 Partial billing on contract 1,000,000. 4,200,000 Accounts receivable 1,000,000 3,000,000 Construction cost 1,050,000 1,920,000 Construction in progress 1,220,000 3,640,000 What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively? 2021 2022 A.220,000. 2,280,000 B.170,000. 500,000 C.220,000. 1,000,000 D.170,000. 1,280,000arrow_forwardIndarrow_forwardAssume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit Estimated loss. 2023 *$2,928,960+ $1,647,540 $1,017,000 3,051,000 968,000 817,000 The revised estimates for the bridge contract are as follows. 2024 $2,928,960 1,647,540 2,418,000 1,897,000 2025 $4,576,500 1,134,000 0 1,806,000 2023 Original Estimates 2024 Revised Estimates $4,520,000 $4,520,000 4,068,000 4,576,500* $452,000 $(56,500) Under the percentage-of-completion method, how would Sunland record the long-term contract revenues, expenses, and losses in 2024. Please show…arrow_forward
- Assume that Sunland Construction Company has a non-cancellable contract to construct a $4,520,000 bridge at an estimated cost of $4,068,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit 2023 Estimated loss $1,017,000 3,05 1,000 968,000 The revised estimates for the bridge contract are as follows. 817,000 4,068,000 2024 $2,928,960 $452,000 1,647,540 2,418,000 1,897,000 2025 $4,576,500 2023 Original Estimates 2024 Revised Estimates $4,520,000 $4,520,000 1,134,000 1,806,000 0 4,576,500* $(56,500)arrow_forwardroad was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). Cost incurred during the year. Estimated costs to complete as of year-end 2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash,…arrow_forwardBlossom Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.3 million. Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract: Costs incurred during the year Estimated costs to complete Revenue Expenses Gross Profit Calculate the gross profit to be recognized each year using the completed-contract method. $ 2022 $661,000 $822,000 1,519,000 705,000 2023 2022 2024 $685,900 0 2023 $ 2024arrow_forward
- Current Attempt in Progress In 2025, Carla Vista Construction Corp. began construction work under a 3-year contract. The contract price was $1,100,000. Carla Vista uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2025, are shown below. Accounts receivable Construction in process Balance Sheet Less: Billings Costs and recognized profit in excess of billings Income Statement $64,000 62,400 Income (before tax) on the contract recognized in 2025 Portion of contract billings collected How much cash was collected in 2025 on this contract? $17.400 $16,640 1,600arrow_forwardSandhill Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.8 million. Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract: Costs incurred during the year Estimated costs to complete Revenue Expenses $ Gross Profit $ 2022 2022 $637,000 1,489,000 $844,000 Calculate the gross profit to be recognized each year using the completed-contract method. 2023 $ $ 713,000 2024 $715,900 2023 0 $ $ 2024 SUPPORTarrow_forwardAssume that Ivanhoe Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of $4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit Estimated loss 2023 $1,035,000 3,105,000 *$2,980,800+$1,676,700 955,000 788,000 2025 $2,980,800 $4,657,500 1,676,700 2024 The revised estimates for the bridge contract are as follows. 2,443,000 1,801,000 2023 Original Estimates 2024 Revised Estimates $4,600,000 $4,600,000 4,140,000 4,657.500* $460,000 1,202,000 2,011,000 0 $(57,500)arrow_forward
- In 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2021 $ 135 Cash collected on project during 2021 $ 105 Construction in progress, 12/31/2021 $ 207 Estimated percentage of completion during 2021 60 % How much cash remains to be collected by CCC on the project?arrow_forwardThe total estimated cost isarrow_forwardIn 2021, Montana Corp. entered into a contract to begin work on a two-year project. Montana recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $37.5 $140 Actual construction costs incurred in 2021 Cash collected on project during 2021 $105 Construction in progress, 12/31/2021 $210 Estimated percentage of completion during 2021 Selected Amounts O $70,000,000 What is the amount of gross profit on the project recognized by Montana during 2021? O $60,000,000 $35,000,000 O $105,000,000 50 %arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning

Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning