Manufacturing Cycle Time:
The time taken from ordering raw material inventory to putting it in manufacturing production process to producing the finished goods . this can be categorized into following components as below
- Process Time : The actual time taken in processes where the raw material is converted into finished goods . This is also called value added activity which can be reduced by using various techniques like kaizen which is continuous improvement technique
- Inspection Time : The time taken for inspection of quality of raw material , work in process at different process end and finished goods . This is part of non value added activity
- Move Time : The time taken for movement of raw material and work in process goods and people between different process . This is part of non value added activity
- Wait time : The time taken between getting the production order and ordering the raw material inventory and actual arrival at production floor and during the process . This is part of non value added activity
The formula to calculate manufacturing cycle time is given below
Manufacturing Cycle Efficiency:
This is ratio which calculated the total time spend on value added activity from the total manufacturing cycle time and is represented in percentage terms
The formula to calculate manufacturing cycle efficiency is given below
The manufacturing cycle time
The manufacturing cycle time is 15 days
Following information is given
- Process time is 6.0 days is also value added activity time
- Inspection time is 0.8 days
- Move time is 3.2 days
- Wait time is 5.0 days
The formula to calculate manufacturing cycle time is given below
The manufacturing cycle time is 15 days
The manufacturing cycle efficiency is 40%
Following information is given
- Process time is 6.0 days also value added activity time
- Inspection time is 0.8 days
- Move time is 3.2 days
- Wait time is 5.0 days
The formula to calculate manufacturing cycle time is given below
The formula to calculate manufacturing cycle efficiency is given below
The manufacturing cycle efficiency is 40% which shows 60% time is spend on non value added activities which should be reduced to bring more efficiency in the production process and resulting in faster delivery to customer
The revised manufacturing cycle efficiency is 54.55%
Following information is given
- Process time is 6.0 days also value added activity time
- Inspection time is 0.8 days
- Revised Move time is 2 days
- Revised Wait time is 2.2 days
The formula to calculate manufacturing cycle time is given below
The formula to calculate manufacturing cycle efficiency is given below
The manufacturing cycle efficiency has increased to 54.55% which shows reduction in non value added activities to 45.45% from previous non value added activities of 60% . Which has brought more efficiency in the production process and resulting in faster delivery to customer?

Want to see the full answer?
Check out a sample textbook solution
Chapter D Solutions
FUND.ACCT.PRIN.-CONNECT ACCESS
- In the month of September, a department had 9,500 units in beginning work in process that were 60% complete. During September, 28,500 units were transferred into production from another department. At the end of September, there were 5,500 units in ending work in process that were 50% complete. Materials are added at the beginning of the process, while conversion costs are incurred uniformly throughout the process. A. The equivalent units of production for materials in September were __. B. The equivalent units of production for conversion costs for September were __.arrow_forwardBurson Enterprises' May 31 bank reconciliation shows deposits in transit of $850. The general ledger Cash in Bank account shows total cash receipts during June of $48,500. The June bank statement shows total cash deposits of $44,300 (including $1,500 from the collection of a note; the note collection has not yet been recorded by Burson). What amount of deposits in transit should appear in the June 30 bank reconciliation?arrow_forwardComputer the production cost per unit under variable costingarrow_forward
- Please provide problem with accountingarrow_forwardGeneral accounting questionarrow_forwardJob 528 was one of the many jobs started and completed during the year. The job required $11,200 in direct materials and 40 hours of direct labor time at a total direct labor cost of $12,600. If the job contained five units and the company billed at 65% above the unit product cost on the job cost sheet, what price per unit would have been charged to the customer?arrow_forward
- Calculate the net cash provided by operating activities of this financial accounting questionarrow_forwardgiven answer of this General accounting questionarrow_forwardBurson Enterprises' May 31 bank reconciliation shows deposits in transit of $850. The general ledger Cash in Bank account shows total cash receipts during June of $48,500. The June bank statement shows total cash deposits of $44,300 (including $1,500 from the collection of a note; the note collection has not yet been recorded by Burson). What amount of deposits in transit should appear in the June 30 bank reconciliation? Helparrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education