Concept explainers
Concept Introduction:
Activity based costing:
Activity based costing can be defined as the costing that assigns cost by assigning costs using factors like cost pools related to a particular overhead and then assign the costs to the products.
Manufacturing
Manufacturing overheads can be defined as the overheads incurred during the manufacturing process of the product. Only the plant or factory related expenses are termed as manufacturing overheads.
Predetermined overhead rate:
Predetermined overhead rate can defined as the rate allocated on the bases of estimated overheads and a base that can used to determine per unit of allocation of overhead of the base.
Requirement 1
To compute:
Activity overhead rate using ABC
Answer to Problem 1BPSB
Solution:
Production Activity | Activity overhead rate |
Wrapping | 5 |
Assembling | 20 |
Product design | 60 |
Obtaining business license | 5 |
Cooking | 270 |
Explanation of Solution
The above answer can be explained as under –
Given,
• Wrapping overheads = $ 500,000 (i.e. $ 300,000 + $ 200,000)
• Assembling overheads = $ 400,000
• Product design overheads = $ 180,000
• Obtaining business license overheads = $ 100,000
• Cooking overheads = $ 270,000 (i.e. $ 150,000 + $ 120,000)
• Units produced = 100,000 units
• Direct labor hours = 20,000 hours
• Design hours = 3,000 hours
• Batches = 1,000 batches
Production Activity | Overheads (A) | Cost pools used | Cost pools given (B) | Activity overhead rate (A) X (B) |
Wrapping | 500,000 | Units | 100,000 | 5 |
Assembling | 400,000 | Direct labor hours | 20,000 | 20 |
Product design | 180,000 | design hours | 3,000 | 60 |
Obtaining business license | 100,000 | Direct labor hours | 20,000 | 5 |
Cooking | 270,000 | Batches | 1,000 | 270 |
Thus, the activity overhead rates have been calculated.
Requirement 2
To determine:
Cost assigned to –
1. Holiday Basket
2. Executive Basket
Answer to Problem 1BPSB
Solution:
Cost assigned to –
1. Holiday Basket = $ 114,000
2. Executive Basket = $ 73,900
Explanation of Solution
The above answer can be explained as under –
1. For Holiday Basket –
Given,
Activity overhead rates –
Production Activity | Activity overhead rate |
Wrapping | 5 |
Assembling | 20 |
Product design | 60 |
Obtaining business license | 5 |
Cooking | 270 |
• Number of units = 8,000 hours
• Direct labor hours = 2,000 hours
• Design hours = 40 design hours
• Batches = 80 batches
Production Activity | Cost pools used | Cost pools given (A) | Activity overhead rate (B) | Total overheads for each activity (A) X (B) |
Wrapping | Units | 8,000 | 5 | 40,000 |
Assembling | Direct labor hours | 2,000 | 20 | 40,000 |
Product design | design hours | 40 | 60 | 2,400 |
Obtaining business license | Direct labor hours | 2,000 | 5 | 10,000 |
Cooking | Batches | 80 | 270 | 21,600 |
Total overheads | 114,000 |
2. For Executive Basket –
Given,
Activity overhead rates –
Production Activity | Activity overhead rate |
Wrapping | 5 |
Assembling | 20 |
Product design | 60 |
Obtaining business license | 5 |
Cooking | 270 |
• Number of units = 1,000 units
• Direct labor hours = 500 hours
• Design hours = 40 design hours
• Batches = 200 batches
Production Activity | Cost pools used | Cost pools given (A) | Activity overhead rate (B) | Total overheads for each activity (A) X (B) |
Wrapping | Units | 1,000 | 5 | 5,000 |
Assembling | Direct labor hours | 500 | 20 | 10,000 |
Product design | design hours | 40 | 60 | 2,400 |
Obtaining business license | Direct labor hours | 500 | 5 | 2,500 |
Cooking | Batches | 200 | 270 | 54,000 |
Total overheads | 73,900 |
Thus, the costs assigned to holiday Basket and executive Basket have been determined.
Requirement 3
To determine:
Overhead cost per unit for –
1. Holiday Basket
2. Executive Basket
Answer to Problem 1BPSB
Solution:
Overhead cost per unit for –
1. Holiday Basket = $ 14.25
2. Executive Basket = $ 73.90
Explanation of Solution
The above answer can be explained as under –
1. For Holiday Basket –
Given,
• Total overhead assigned = $ 114,000 (computed in requirement 2)
• Number of units = 8,000 units
2. For Executive Basket –
Given,
• Total overhead assigned = $ 73,900 (computed in requirement 2)
• Number of units = 1,000 units
Thus, the overhead cost per unit for holiday and executive have been calculated.
Requirement 4
To determine:
Overhead cost if a single plantwide overhead rate is used for –
1. Holiday Basket
2. Executive Basket
Answer to Problem 1BPSB
Solution:
Overhead cost if a single plantwide overhead rate is used for –
1. Holiday Basket = $ 18.13 per unit
2. Executive Basket = $ 36.25 unit
Explanation of Solution
The above answers can be explained as under –
Given,
• Wrapping overheads = $ 500,000 (i.e. $ 300,000 + $ 200,000)
• Assembling overheads = $ 400,000
• Product design overheads = $ 180,000
• Obtaining business license overheads = $ 100,000
• Cooking overheads = $ 270,000 (i.e. $ 150,000 + $ 120,000)
• Direct labor hours = 20,000 hours
Total overhead will be calculated –
Now, per direct labor hour rate will be calculated –
Now, the overhead cost per unit will be calculated –
1. For Holiday Basket –
Given,
• Direct labors used = 2,000 hours
• Number of units = 8,000 units
• Per direct labor hour rate = $ 72.50
2. For Executive Basket –
Given,
• Direct labors used = 500 hours
• Number of units = 1,000 units
• Per direct labor hour rate = $ 72.50
Thus, the overhead cost if a single plantwide overhead rate is used has been determined.
Requirement 5
To compare:
Overhead costs per unit computed in requirements 3 and 4 and explain which method was more appropriate
Answer to Problem 1BPSB
Solution:
The costs in the two requirements can be computed as under –
Holiday Basket | Executive Basket | |
Activity based cost per unit | 14.25 | 73.9 |
Plantwide cost per unit | 18.13 | 36.25 |
The activity based costing per unit is providing a more accurate cost per unit as activity based costing focuses on the consumption of resources and assigns costs accordingly whereas plantwide rate assigns costs on the basis of number of units produced and direct labors used only. The activity based costing is a better measure as it is using the actual use of resources rather than the plant wide rate, it is ignoring all the other factors.
Explanation of Solution
The above answer can be explained as under –
For the holiday basket, the activity based cost per unit is $ 14.25 and plantwide rate is 18.13 per unit as it is a high-volume product. While for executive basket, the activity based cost per unit is $ 73.90 and plantwide rate is $ 36.25 per unit as it is a low-volume product. This is a clear indication that, activity based costing is taking into consideration all the resources and then assigning the costs to the products, while plantwide rate assigns costs on the basis of number of units produced and direct labors used only. For this reason only, the plant-wide overhead rate for holiday basket is low as it is a high-volume product while the plant-wide overhead rate for executive basket is high as it is a low-volume product clearly stating the rates are not properly allocated.
Thus, the two methods have been compared and explained.
Want to see more full solutions like this?
Chapter C Solutions
Connect Access Card for Fundamental Accounting Principles
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education