a.
To determine: NPV (
Introduction: The net present value helps to an organization for taking decisions regarding the growth of investment and the business. It analyzes the profitability of the project through capital budgeting.
a.
Answer to Problem 8PS
$18,092,131.90 is the Net
Explanation of Solution
Given Information:
The beta value, risk free rate of interest, expected return on market is given.
Net present value is the discounting of present value of
Calculation of net Present Value,
“C” refers to the cash flow,
“I” refers to discount rate
“t” refers to the time for cash flow
The
Calculating the NPV of the project,
So the Net Present Value is $18,092,131.90
b.
To determine: The highest possible beta for the project
Introduction: The net present value helps to an organization for taking decisions regarding the growth of investment and the business. It analyzes the profitability of the project through capital budgeting.
b.
Answer to Problem 8PS
3.47 is the highest possible value of beta for the project.
Explanation of Solution
Given Information:
The risk free rate of interest, expected return on market is given.
Net present value is the discounting of present value of cash inflow and outflow at a specified rate. When the NPV becomes positive, then the investment is profitable. It analyzes the profitability of the project.
At
YEAR | CASH FLOW ($) |
0 | -40,000,000 |
1 | 15,000,000 |
2 | 15,000,000 |
3 | 15,000,000 |
4 | 15,000,000 |
5 | 15,000,000 |
6 | 15,000,000 |
7 | 15,000,000 |
8 | 15,000,000 |
9 | 15,000,000 |
10 | 15,000,000 |
IRR | 35.7333% |
The calculation of Beta,
Before the NPV becomes negative, the highest value of beta is 3.47
Want to see more full solutions like this?
Chapter 9 Solutions
INVESTMENTS(LL)W/CONNECT
- A project is thought to have a 0.55 probability of making a profit of P400,000 and a 0.45 probability of making a profit of P200,000. What is the change in expected profit if the probabilities actually turn out to be 0.60 and 0.40, respectively?arrow_forwardCelestial Crane Cosmetics is analyzing a project that requires an initial investment of $3,225,000. The project's expected cash flows are: Year Cash Flow Year 1 $375,000 Year 2 -125,000 Year 3 500,000 Year 4 400,000 If the company's WACC is 8% and the project has the same risk as the firm's average project, what is the project's modified internal rate of return (MIRR)? Should you accept or reject this project?arrow_forwardDed You are a consultant to a large manufacturing corporation that is considering a project with the following net after-tax cash flows (in millions of dollars): Years from Now 0 1-10 After-Tax Cash Flow -30 14 The project's beta is 1.6. a. Assuming that r = 48 and E(M)= 18%, what is the net present value of the project? (Do not round intermediate calculations. Enter your answer in millions rounded to 2 decimal places.) Net present value b. What is the highest possible beta estimate for the project before its NPV becomes negative? (Round your answer to 2 decimal places.) Highest betaarrow_forward
- You are a consultant to a large manufacturing corporation considering a project with the following net after-tax cash flows (in millions of dollars). After-Tax Year from Now CF O 1-9 year 10 -20 10 per 20 The project's beta is 1.7. Assuming that the risk-free rate is 9% and the expected rate of return on the market portfolio is 19%. What is the net present value of the project? Your answer should be in millions of dollars and accurate to the hundredth. For example, if your answer is 3.478 million dollars, then type in 3.48.arrow_forwardA company is considering a project that has the following cash flows: C0 = -5,000, C1 = +900, C2 = +2,500, C3 = +1,100, and C4 = +2,900 with a risk-adjusted discount rate of 12%. Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Profitability Index, and the Payback of this project. If you were the manager of the firm, will you accept or reject the project based on the calculation results above?arrow_forwardYou are a consultant to a large manufacturing corporation that is considering a project with the following net after-tax cash flows (in millions of dollars): Years from Now After-Tax Cash Flow -30 1-10 14 The project's beta is 1.6. 18%, what is the net present value of the project? (Do not round intermediate calculations. a. Assuming that rf = 4% and E(rM) Enter your answer in millions rounded to 2 decimal places.) Net present value b. What is the highest possible beta estimate for the project before its NPV becomes negative? (Round your answer to 2 decimal places.) Highest betaarrow_forward
- 3. You are considering a project that has an initial outlay of $1million. The profitability index of the project is 2.24. What is the NPV of the project?arrow_forwardYour firm has limited capital to invest and is therefore interested in comparing projects based on the profitability index (PI), as well as other measures. What is the PI of the project with the estimated cash flows below? The required rate of return is 18.1%. Round to 3 decimals. Year 0 cash flow = 720,000 Year 1 cash flow = -130,000 Year 2 cash flow = 540,000 Year 3 cash flow = 490,000 Year 4 cash flow = 480,000 Year 5 cash flow = 550,000 Answer:arrow_forwardCompute the NPV statistic for Project Y. Explain whether or not the firm should accept or reject the project with the cash flows shown in the chart below if the appropriate cost of capital is 10%. Year 0 = -8,000, year 1 = 3,350, Year 2 = 4,180, Year 3 = 1,520, Year 4 = $300arrow_forward
- Your firm has limited capital to invest and is therefore interested in comparing projects based on the profitability index (PI), as well as other measures. What is the PI of the project with the estimated cash flows below? The required rate of return is 16.7%. Round to 3 decimals. Year 0 cash flow = -720,000 Year 1 cash flow = -160,000 Year 2 cash flow = 540,000 Year 3 cash flow = 500,000 Year 4 cash flow = 430,000 Year 5 cash flow = 470,000arrow_forwardYou are a consultant to a large manufacturing corporation considering a project with the following net after-tax cash flows (in millions of dollars): Years from Now 0 1 to 10 After-Tax CF -$29 $15. The project's beta is 1.8. Assuming r = 6% and B(r) = 16% Required: a. What is the net present value of the project? (Do not round intermediate calculations. Enter your answer in millions rounded to 2 decimal places.) Net present value million b. What is the highest possible beta estimate for the project before its NPV becomes negative? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Highest possible beta valuearrow_forwardFind the modified internal rate of return (MIRR) for a proposed project costing $5,489. Assume that the appropriate cost of capital for projects of this risk level, at this company is 11.46%, and the estimated cash flows for the life of the project are found in the table below. (If you calculate an MIRR of 20.22%, please enter 20.22 - do not include the % symbol, and use at least two decimal places). Year 1 Year 2 Year 3 Year 4 Year 5 $6,100 $10,836 $9,527.1 $13,000 $7,285arrow_forward
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT