a.
Ascertain the unit cost for each of the three jobs started and completed using the current costing system.
a.
Explanation of Solution
Activity-based costing:
Activity-based costing refers to the method of costing where the
Ascertain the unit cost for each of the three jobs started and completed using the current costing system:
Using the direct-labor cost, the predetermined rate using the traditional system is calculated. For the coming year, 16,000 direct-labor hours is estimated by the cost analyst, and an hour of direct labor costs $25 on average. Hence, the estimation of the annual direct-labor cost is $400,000
300% of direct-labor cost
Using the traditional system, the cost of each of the jobs are:
Particulars | Job 1101 | Job 1102 | Job 1103 |
Direct materials | $4,000 | $6,000 | $5,000 |
Direct labor | 10,000 | 16,000 | 13,000 |
Overhead (@300%) | 30,000 | 48,000 | 39,000 |
Total cost | $44,000 | $70,000 | $57,000 |
Number of units | 200 | 500 | 400 |
Unit cost | $220.00 | $140.00 | $142.50 |
Table: (1)
Hence, the unit cost for each of the three jobs started and completed are $220.00, $140.00, and $142.50, respectively.
b.
Ascertain the unit cost for each of the three jobs started and completed using the ABC system.
b.
Explanation of Solution
Compute the unit product cost:
Particulars | Job 1101 | Job 1102 | Job 1103 |
Direct materials | $4,000 | $6,000 | $5,000 |
Direct labor | 10,000 | 16,000 | 13,000 |
Overhead: | |||
Machining | 10,000(1) | 14,000 | 12,000 |
Assembly | 3,000(2) | 10,000 | 4,500 |
Setup labor | 4,000(3) | 8,000 | 4,000 |
Packaging | 300(4) | 750 | 600 |
Compliance testing | 5,000(5) | 0 | 5,000 |
Total costs | $36,300 | $54,750 | $44,100 |
Number of units | 200 | 500 | 400 |
Unit cost | $181.50 | $109.50 | $110.25 |
Table: (2)
Working Note (1):
Calculate the machining overhead.
Working Note (2):
Calculate the assembly overhead.
Working Note (3):
Calculate the Setup labor overhead.
Working Note (4):
Calculate the Packaging overhead.
Working Note (5):
Calculate the Machining overhead.
Working Note (6):
Calculate the cost per machine-hour.
Working Note (7):
Calculate the cost per labor-hour.
Working Note (8):
Calculate the cost per run.
Working Note (9):
Calculate the cost per unit.
Working Note (10):
Calculate the cost per order tested.
Want to see more full solutions like this?
Chapter 9 Solutions
FUNDAMENTALS OF COST ACCOUNTING IA
- Quick answer of this accounting questionsarrow_forwardCan you please answer the general accounting question?arrow_forwardThe actual cost of direct materials is $55.75 per pound. The standard cost per pound is $60.50. During the current period, 6,100 pounds were used in production. The standard quantity for actual units produced is 5,700 pounds. How much is the direct materials price variance? A. $27,075 unfavorable B. $28,975 unfavorable C. $28,975 favorable D. $27,075 favorablearrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education