The given problem is such that PSI believes that it will need the following amounts of generating capacity during the next five years.

The data is given in the table below:

TABLE 1:

YearGenerating capacity (million kwh)
180
2100
3120
4140
5160

Further the company has a choice of building (and then operating) power plants with the specifications shown in the table below:

TABLE 2:

PlantGenerating capacity (million kwh)Construction cost ($ million)Annual operating cost ($ million)
170201.5
250160.8
360181.3
440140.6

Now considering this information, an IP is to be formulated to minimize the total cost of meeting the generating capacity requirements of the next five years.

Start with defining decision variables for each decision that the PSI must take to minimize the total cost of meeting the generating capacity requirements of the next five years. Thus define “0 – 1” variables as:

Again assume “0 – 1” decision variables related to the plant operation at each operation at each year as:

Here, “i = 1, 2, 3, 4” and “t = 1, 2, 3, 4, 5”

Here the company has a choice of building and then operating power plants thus construction cost will be bore once for each power plant however annual operating cost of each power plant will have to be paid each subsequent year for carrying operation.

Such as, any plant will be constructed in either one of the five years thus will require one time construction cost.

Suppose, if plant 1 is constructed in the first year then we must have x11 = 1 and the rest x12 = x13 = x14 = x15 = 0.

Therefore, construction cost for plant 1 will be, 20(x11 + x12 + x13 +x13 +x14 + x15)

Similarly, construction cost for other plants will be defined as:

The construction cost for plant 2 will be,

Plant 2:

16(x21+ x22 + x23 + x24 + x25)

The construction cost for plant 3 will be,

Plant 3:

18 (x31 +x32 +x33 +x34 +x35)

The construction cost for plant 4 will be,

Plant 4:

14 (x41 + x42 +x43 +x43 + x45)

Now the annual operating cost of any plant is to be paid only for that year during which year it is in operation that is yit = 1 otherwise yit = 0.

Thus, using the table given above the annual operating cost for each plant will be defined as:

Plant 1:

1.50 (y11 + y12 + y13 + y14 + y15)

Plant 2:

0.8 (y21 +y22 + y23 + y24 + y25)

Plant 3:

1.3(y31 + y32 + y33 + y34 + y35)

Plant 4:

0.6(y41 +y42 + +y43 + y44 + y45)

Now using the above results, an optimization function to minimize the total cost of meeting the generating capacity requirements of the next five years is,

min z = 20 (x11 +x12 + x13 + x 14 + x15) + 16(x21 + x22 + x23 + x24 +x25)

            + 18 (x31 + x32 +x33 +x34 + x35) + 14 (x41 +x42 + x43 + x44 + x45)

  + 1...

Blurred answer
Students have asked these similar questions
hi, I need help to resolve the case, thank you
The following table shows the timestamp and actions by two users. Choose the best option that describes the outcome of the actions. Time JohnSara 10:14 select* from hr.employees; 10:15 Update hr.employees set salary= 100  where employee_id= 206; 10:16 Commit:  Select* from hr.employees; 10:18 Commit: 10:20 Select* from hr.employees;  Commit:   John's query willreturn the same results all three times it is executed as they are run in the same session.   John's queries run at10:16 and10:20 produce the same result, which is different from the one at 10:14   John's query run at 10:16 waits until 10:18 to produce results, waiting for the commit to happen.   John's queries run at 10:14 and 10:16 produce the same result, which is different from the one at 10:20
what's the process used to obtain IP configuration using DHCP in Windows Server.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Text book image
Np Ms Office 365/Excel 2016 I Ntermed
Computer Science
ISBN:9781337508841
Author:Carey
Publisher:Cengage