Operations and Supply Chain Management 9th edition
9th Edition
ISBN: 9781119320975
Author: Roberta S. Russell, Bernard W. Taylor III
Publisher: WILEY
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 9, Problem 10Q
Which method for determining activity time estimates, deterministic or probabilistic, do you perceive to be preferable? Explain.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which method for determining activity time estimates,deterministic or probabilistic, do you perceive to be preferable? Explain.
The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Following are five projects under consideration. Criteria Strong sponsor Supports business strategy Urgency 10% of sales from new products Competition Fill market gap Weight 2 4 2 5 1 2 Project 1 6 8 9 5 4 0 Project 2 9 8 4 2 7 10 Project 3 3 2 3 9 4 8 Project 4 9 6 6 1 4 0 Project 5 6 0 7 4 1 0 Using the scoring matrix above, what score would you give to each project?
What is an activity slope and what does it indicate?
Chapter 9 Solutions
Operations and Supply Chain Management 9th edition
Ch. 9 - Why is CPM/PERT a popular and widely applied...Ch. 9 - What is the purpose of a CPM/PERT network?Ch. 9 - Why are dummy activities used in a CPM/PERT...Ch. 9 - What is the critical path, and what is its...Ch. 9 - What is slack, and how is it computed?Ch. 9 - How are the mean activity times and activity...Ch. 9 - How is total project variance determined in...Ch. 9 - What is the purpose of project crashing analysis?Ch. 9 - Describe the process of manually crashing a...Ch. 9 - Which method for determining activity time...
Ch. 9 - Explain how a Gantt chart differs from a CPM/PERT...Ch. 9 - Discuss the relationship of direct and indirect...Ch. 9 - Describe the limitations and disadvantages of...Ch. 9 - Describe the difference between activity-on-node...Ch. 9 - Identify and briefly describe the major elements...Ch. 9 - Select an everyday project you are familiar with...Ch. 9 - Prepare a WBS for a spaghetti with meatballs...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Use the project activities that follow to...Ch. 9 - Construct a network from the information in the...Ch. 9 - For the network in Problem 9.4, determine the...Ch. 9 - Given the following network with activity times in...Ch. 9 - Given the following network with activity times in...Ch. 9 - A marketing firm is planning to conduct a survey...Ch. 9 - In one of the little-known battles of the Civil...Ch. 9 - A group of developers is building a new shopping...Ch. 9 - The management of a factory is going to erect a...Ch. 9 - Given the following network and probabilistic...Ch. 9 - The Farmers American Bank of Leesburg is planning...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The schedule Dr. Barr set up worked well at the clinic where she was a resident. What are some of the reasons w...
Operations Management, Binder Ready Version: An Integrated Approach
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
3. Briefly describe the contributions of the four individuals identified in the preceding question.
Operations Management
Create an Excel spreadsheet on your own that can make combination forecasts for Problem 18. Create a combinatio...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
13. Explain the value of seasonal indices in forecasting. How are seasonal patterns different from cyclical pat...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Consider the sales data for Computer Success given in Problem 7. Use a 3-month weighted moving average to forec...
Operations Management: Processes and Supply Chains (11th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Discuss in brief slack variables?arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Activity Optimistic Most Probable Pessimistic Immediate Predecessors A 1 2 3 - B 4 6 8 A C 2 4 6 A D 1 2 3 B, C E 2 3 4 B F 1 2 3 A G 1 2 3 D H 1 2 3 G I 1 1 1 E, H, F A. Draw a project network for this problem. B. Fill in all the blanks in the following table. Note: For variance (σ2) in activity time, keep two decimal places. Activity Expected Time t (weeks) Variance σ2 ES EF LS LF Slack Critical Path? A B C D…arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Activity Optimistic Most Probable Pessimistic Immediate Predecessors A 1 2 3 - B 4 6 8 A C 2 4 6 A D 1 2 3 B, C E 2 3 4 B F 1 2 3 A G 1 2 3 D H 1 2 3 G I 1 1 1 E, H, F Draw a project network for this problem. Fill in all the blanks in the following table. Note: For variance (σ2) in activity time, keep two decimal places. Activity Expected Time t (weeks) Variance σ2 ES EF LS LF Slack Critical Path? A B C D…arrow_forward
- The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Activity Optimistic Most Probable Pessimistic Immediate Predecessors A 1 2 3 - B 4 6 8 A C 2 4 6 A D 1 2 3 B, C E 2 3 4 B F 1 2 3 A G 1 2 3 D H 1 2 3 G I 1 1 1 E, H, F a. Draw a project network for this problem. b. Fill in all the blanks in the following table. c. What is the expected time and variance to complete the project? Note: For variance (σ2) in activity time, keep two decimal places. Activity Expected Time t (weeks) Variance σ2 ES EF LS LF Slack Critical Path? A B C…arrow_forwardCan anybody draw a network analysis diagram of this problem?arrow_forwardOPERATIONS Duration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 Use either PERT or CPM to (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Re-schedule the activities for smooth development (iii) Find the project schedule if only 4 men are availablearrow_forward
- What are the considerations in planning for location, facilities and capacity?arrow_forwardStarts With a Bang, Ends With a Whimper A faculty member, Kim Green from the Management Department, was asked to chair a major university committee to plan the mission of the university for the next 20 years. Three other senior faculty and seven administrators from across the campus were also asked to serve on this committee. The president of the university, Dr. Sulgrave, gave the commit- tee its charge: What should Northcoast University be like in the year 2020? Dr. Sulgrave told the committee that the work of this task force was of utmost importance to the future of the university, and the charge of this committee should take precedence over all other matters. The task force was allowed to meet in the president’s conference room and use the president’s secretary. The report of the committee was due in 2 months. The task force members felt very good about being selected for such an important team. The team met on a weekly basis for about 2 hours each time. At first, the members were…arrow_forwardTools View Week 3 Bonus Activity- DEMAND FORECASTING CASE STUDY After reviewing the forecasting demonstration and looking over the slides, complete the following case activity and transfer your answers to the appropriate questions in the Canvas activity quiz. You have been hired as a demand planning intern for Hawaiian Island Creations (HIC). They want you to de- velop a forecast for their HIC Papanui style of sun- glasses. The goal is to determine how many pair they will produce to meet retailer demand in July 2021. During your first meeting, you were handed some data to work with and the product team talked about the company's upcoming promotional blitz to support Summer Break '21 in major vacation destinations. Month Forecast Demand January 2021 4.000 3,300 February 2021 4,200 3,900 March 2021 4,500 4,300 April 2021 4.800 4,200 May 2021 5 000 5.400 of 4 P Type here to search 立arrow_forward
- Angel healthcare Ltd., has 2 investment opportunities, each costing $120000 and each have expected profit as shown below: Years Project "A' Project "B' ($) ($) 1 40000 30000 2 30000 40000 3 20000 35000 4 15000 30000 Year 1 2 3 PVIF @ 10% 0.909 0.826 0.751 4 0.683 Compute NPV & Profitability Index, Suggest which Project to be preffered at 10%cost of capitalarrow_forwardThe manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 8 Reserve pool A 4. 6 D Announce program В, с 3 E Meet with coaches B 4 F Order team suits A 1 2 3 G Register swimmers D 2 3 H Collect fees G 1 I Plan first practice Е, Н, F 1 1 1 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to two decimal places.) Earliest Start Earliest Finish Latest Latest Activity Slack Start Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in weeks)? (Round your answer to two decimal…arrow_forwardThe Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following table: Construct the project network for this project and determine the following: a. Expected activity times b. Earliest and latest activity times and activity slack c. Critical path d. Expected project duration and variance e. The probability that the mill will be fined $300,000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY