![Solid Waste Engineering](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_largeCoverImage.gif)
Concept explainers
(a)
The total density of the refuse.
![Check Mark](/static/check-mark.png)
Answer to Problem 8.3P
The total density is
Explanation of Solution
Given data:
The following table shows the mass of materials.
Component | Percent by weight |
Food waste | 10 |
Yard waste | 20 |
Mixed paper | 40 |
Corrugated cardboard | 100 |
Glass | 10 |
Ferrous(cans) | 10 |
Table (1)
Concept used:
Write the expression to calculate the total density.
Here, mass of material is
The following table shows bulk density of given materials.
Component | Bulk Densities |
Food waste | 23.04 |
Yard waste | 4.45 |
Mixed paper | 3.81 |
Corrugated cardboard | 1.87 |
Glass | 18.45 |
Ferrous (cans) | 6.36 |
Table (2)
Calculation:
Calculate the total density.
Substitute
Conclusion:
The total density is calculated by mass of materials and density and their components.
(b)
The bulk density of the refuse.
![Check Mark](/static/check-mark.png)
Answer to Problem 8.3P
The bulk density of refuse is
Explanation of Solution
Given data:
The following table shows the bulk density of the recovered refuse.
Component | Percentage recovered |
Garbage | 0 |
Yard waste | 0 |
Mixed paper | 50 |
Glass | 60 |
Ferrous(cans) | 95 |
Table (3)
Concept used:
Write the expression to calculate the not recovered mass of material.
Here, the not recovered mass of material is
Write the expression to calculate the total density of refuse.
Here, the density of the recovered refuse is
Calculation:
Calculate the density of the not recovered refuse.
Substitute
Here,
Calculate the density of the recovered refuse.
Substitute
Calculate the total density of the landfill.
Substitute
Conclusion:
The bulk density is calculated using the density of the recovered refuse, not recovered, recovered mass of material and not recovered mass of material.
(c)
![Check Mark](/static/check-mark.png)
Answer to Problem 8.3P
Explanation of Solution
Given data:
Original life of landfill is
Calculation:
Calculate the expected life of landfill.
Here, the expected life of the landfill is
Substitute
Conclusion:
Thus, the expected life for landfill is
Want to see more full solutions like this?
- Olin's Construction: Principles, Materials, and Methods By H. Leslie Simmonsarrow_forwardThe L6 x 4 x 1/2 single angle shown has two rows of bolts. Each leg has one row (one line) of 5/8 in bolts in each leg as shown. Determine the net area (An). If needed, I attached the section properties from AISC manual for L6x4x1/2.arrow_forward3. Determine the reactions at the supports for the frame shown in following. 36.5 kN/m 14.6 kN/m Hinge R = 10 m 10 m -10 marrow_forward
- # 4 F3 Existing Flocculation Basin Design Parameters at 22.5 MGD: A) # of Basins: 5 B) # of Stages per Basin: 2 c) Basin Dimensions: (30 ft. X 4 ft. X 15 ft.) D) Volume per Basin 10,800 cf (80,787 Gal) E) Total Flocculation Volume: 54,000 cf (406,920 Gal) F) Theoretical Unit Detention Time: 25.9 minutes G) Flow through Velocity (Q): 1.16 ft/min Deliverables: 1) Determine if the existing flocculation basins are sufficient to accommodate the projected future capacity. A) Current Capacity: 22.5 MGD B) Future Capacity: 34.5 MGD for 110,000 residents C) If not, determine the number of additional flocculation basins needed to accommodate the future capacity of 34.5 MGD. a) Ignore this bullet point 2) Specify the basic dimensions (length, width, water height, weir dimensions, etc.) of these additional flocculation basins. 3) Specify the design flow rate, detention time, and the flow-through velocity for each basin under the maximum future capacity of 34.5 MGD, assuming one of the basins is…arrow_forwardA1.4- Determine the factored moment resistance for the flanged beam (simply supported) shown in Figure 4. Given: Beam span L = 8m fc = 25MPa fy=400MPa As = 3-35M *350* mm 1.5 m Figure 4 *350* mm -60mmarrow_forwardA2.3- a simply supported reinforced concrete beam of rectangular cross-section is shown in Figure 3. The beam supports a uniform dead load of 20 kN/m (excluding the beam self-weight) and a uniform live load of 20 kN/m. The beam width is restricted to 400 mm. The maximum aggregate size is 20 mm. We are using 10M bars for stirrups and 25M bars for tension steel. Concrete is type N with f'c = 35 MPa and fy = 400 MPa. The beam needs to have 2hr fire rating. Design the beam for the given load, considering the reinforcement ratio p < 0.5 pb Figure 3 WDL = 20 kN/m WLL= 20 kN/m 8.0 marrow_forward
- A2.2- For the given reinforced concrete section shown in Figure 2, a) Determine the balanced reinforced amount for this section; b) Calculate the ultimate moment resistance of the section if As = 8-20M. What is the mode of failure? c) Calculate the ultimate moment resistance of the section if As = 8-30M. Determine the strain in the steel reinforcement. Given: fc 30 MPa fy = 400 MPa 625 mm 500 mm + + *. 400 mm Figure 2arrow_forwardA2.1- For a reinforced concrete beam (typical cross-section is shown in Figure 1), a) Determine the maximum moment that this beam can resist before cracking; b) Determine the beam moment of inertia after cracking. Given: The beam is reinforced with 4-25M longitudinal bars f'c = 35 MPa fy = 400 MPa 600 mm 530 mm + * 400 mm * Figure 1arrow_forwardCalculate the number of 8 x 8 x 16 inch blocks needed to complete the wall overhead doors 10 x 12 ft high If Lintel blocks are required wherever the #4 horizontal bars are located and above the doors how many plain blocks and how many lintel blocks are needed for the wall. Show all calculationsarrow_forward
- Calculate the quantity of cubic yards needed for the spread footing usinf a waste factor of 10% Determine the amount of rebar needed for the spread footing, dowels extend 24 inches into the colum Allow for 3 inch concrete cover Show all work pleasearrow_forwarda. Determine the effective area for the case shown in the figure below. Suppose that l = 4 in. For L5 x 5 x 5/8: Ay = 5.90 in.², = 1.47 in. L5 × 5 × 58 Weld (Express your answer to three significant figures.) A₂ = 6.25 in.2 b. Determine the effective area for the case shown in the figure below. Suppose that = 4 in. PL38 x 4 Weld (Express your answer to three significant figures.) A₁ = in.2 c. Determine the effective area for the case shown in the figure below. PL³/8 x 5 Weld (Express your answer to three significant figures.) in, 2 A₁ = d. Determine the effective area for the case shown in the figure below. PL/2 × 51/2 оо 3/4-in.-diam. bolts (Express your answer to three significant figures.) A₂ = in.2 e. Determine the effective area for the case shown in figure below. PL³½ x 6 7/8-in.-diam. bolts (Express your answer to three significant figures.) Ae in.2arrow_forwardAn American Standard Channel shape must resist a factored tensile load. The length is 15 ft, and there will be two lines of 7/8-in. diameter bolts in the web, as shown in the figure below. Estimate the shear lag factor U to be 0.85. (In a practical design, once the member and bolt layout are selected, the value of U could be computed and the member design could be revised if necessary.) Use A36 steel. For the steel Fy = 36 ksi and F₁ = 58 ksi. Try the tension members given in the table below. Tension member A, (in.²) tw (in.) ry (in.) C10 x 20 5.87 0.379 0.690 C3 × 6 1.76 0.356 0.413 C6 × 8.2 2.39 0.200 0.536 C5 × 9 2.64 0.325 0.486 Bolt lines Select an American Standard Channel shape to resist a factored tensile load of 120 kips. A) C10 × 20 B) C3 × 6 C) C6 x 8.2 D) C5 x 9 -Select- V What is the required gross area? (Express your answer to three significant figures.) Ag = in.2 What is the required effective area? (Express your answer to three significant figures.) Ae = in.2 What is…arrow_forward
- Solid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
- Engineering Fundamentals: An Introduction to Engi...Civil EngineeringISBN:9781305084766Author:Saeed MoaveniPublisher:Cengage LearningPrinciples of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage LearningMaterials Science And Engineering PropertiesCivil EngineeringISBN:9781111988609Author:Charles GilmorePublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305635203/9781305635203_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305084766/9781305084766_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970939/9781305970939_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781111988609/9781111988609_smallCoverImage.gif)