CodeHead Software Inc. does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer’s hourly rate to increase to $40.00 per hour during the first week in May.
Instructions
- 1. If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance?
- 2. What was the actual labor time variance as a result of generating 5,650 lines of code?
- 3. What was the labor rate variance as a result of the bonus?
- 4. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been the labor time variance in the first week?
- 5. Which decision is better, paying the bonus or hiring another programmer?
1.
Compute the direct labor time variance, if the team had generated 4,650 lines of code according to the original plan.
Explanation of Solution
Direct labor variances:
The difference between the actual labor cost in the production and the standard labor cost for actual production is known as direct labor cost variance. The direct labor variance can be classified as follows:
- v Labor rate variance.
- v Labor time variance.
Determine the direct labor time variance.
Working note (1):
Compute the actual labor hours:
Working note (2):
Compute the standard direct labor hours:
The direct labor time variance is $448 and it is an unfavorable variance, since the actual direct labor hour is more than the standard direct labor hour.
2.
Compute the actual labor time variance, as a result of generating 5,650 lines of code.
Explanation of Solution
Determine the direct labor time variance.
Working note (3):
The direct labor time variance is $(832) and it is a favorable variance, since the actual direct labor hour is lesser than the standard direct labor hour.
3.
Compute the direct labor rate variance as a result of the bonus.
Explanation of Solution
Determine the direct labor rate variance.
The direct labor rate variance is $1,600 and it is an unfavorable variance, since the actual rate per hour is more than the standard rate per hour.
4.
Compute the labor time variance in the first week if a new employee had been hired from the employment firm.
Explanation of Solution
Determine the direct labor time variance:
Working note (4):
The direct labor time variance is $448 and it is an unfavorable variance, since the actual direct labor hour is more than the standard direct labor hour.
5.
State the decision that would be better, paying the bonus, or hiring another programmer.
Answer to Problem 5PA
Hiring an extra employee is the better decision when compared to paying the bonus as hiring another programmer is less costly.
Explanation of Solution
Determine the total direct labor cost time variance.
The direct labor cost variance for paying the bonus is $768 and it is an unfavorable variance, since the direct labor rate variance is more than the direct labor time variance. The labor cost variance in hiring another programmer would have been $448 which is unfavorable, which is less than the cost of paying the bonus.
Hence, the net benefit of hiring another programmer when compared to paying the bonus is $320
Want to see more full solutions like this?
Chapter 8 Solutions
Managerial Accounting
- How?arrow_forwardI need this question answer general Accountingarrow_forwardAccounting: The warehouse supervisor at Emerald Bay Trading must reconcile damaged goods claims. Their policy allows claims within 48 hours of delivery, requires photographic evidence, and management approval for values over $500. Last week, from 45 deliveries worth $28,000, customers reported 8 damages, submitted 6 photos, and 5 claims met the time limit. What is the value of valid claims if each averages $180?arrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College