Concept explainers
1.
The direct materials cost variance, price variance and quantity variance.
1.
![Check Mark](/static/check-mark.png)
Explanation of Solution
Given,
The actual material used is 1,000,000 lbs.
The standard quantity of materials for actual production is 1,050,000 lbs.
The actual price is $4.25 per lb.
The standard price is $4.00 per lb.
Calculation of direct material cost variance:
Particulars | Amount ($) |
Actual units at actual cost | 4,250,000 |
Standard units at | 4,200,000 |
Direct material cost variance | 50,000 (unfavorable) |
The direct material cost variance is $50,000 (unfavorable).
Calculation of direct material price variance:
The formula to calculate the direct material price variance is,
Substitute 1,000,000 lb. for the actual quantity, $4.25 for the actual price and $4 for the standard price in the above formula.
The direct material price variance is $250,000 (unfavorable).
Calculation of direct material quantity variance:
The formula to calculate the direct material quantity variance is,
Substitute 1,000,000 lb for the actual quantity, 1,050,000 lb for standard quantity and $4.00 for standard price in the above formula.
The direct material quantity variance is $200,000 (unfavorable).
Hence, the direct material cost variance, price variance and quantity variance is $50,000 (unfavorable), $250,000 (unfavorable) and $200,000 (unfavorable).
2.
The direct labor cost, rate and efficiency variances.
2.
![Check Mark](/static/check-mark.png)
Explanation of Solution
Given,
The actual hours used is 250,000 hours.
The standard hours for actual production are 252,000 hours.
The actual rate is $7.75 per hour.
The standard rate is $8.00 per hour.
Calculation of direct labor cost variance:
Particulars | Amount ($) |
Actual hours at actual cost | 1,937,500 |
Standard hours at standard cost | 2,016,000 |
Direct labor cost variance | 78,500 (favorable) |
The direct labor cost variance is $78,500 (favorable).
Calculation of direct labor rate variance:
The formula to calculate the direct labor rate variance is,
Substitute 250,000 hours for the actual hours, $7.75 for the actual rate and $8 for the standard rate in the above formula.
The direct labor rate variance is $62,500 (favorable).
Calculation of direct labor efficiency variance:
The formula to calculate the direct labor efficiency variance is,
Substitute 250,000 for the actual hours, 252,000 for standard hours and $8.00 for standard rate in the above formula.
The direct labor efficiency variance is $16,000 (favorable).
Hence, the direct labor cost variance, rate variance and efficiency variance is $78,500 (favorable), $62,500 (favorable) and $16,000 (favorable).
3.
The
3.
![Check Mark](/static/check-mark.png)
Explanation of Solution
Calculation of the overhead controllable variance:
Particulars | Amount ($) |
Actual overhead incurred ($1,960,000+$1,200,000) | 3,160,000 |
Budgeted overhead (from flexible budget) | 3,276,000 |
Controllable overhead variance | 116,000 (favorable) |
The overhead controllable variance is $116,000 (favorable).
Calculation of the fixed overhead volume variance:
Particulars | Amount ($) |
Budgeted fixed overhead(at 80% capacity) | 2,016,000 |
Fixed overhead | 1,764,000 |
Fixed overhead volume variance | 252,000 (unfavorable) |
The fixed overhead volume variance is $252,000 (unfavorable).
Thus, the overhead controllable variance is $116,000 (favorable) and the fixed overhead volume variance is $252,000 (unfavorable).
Want to see more full solutions like this?
Chapter 8 Solutions
Managerial Accounting - Connect Access
- Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $7,000, direct labor of $3,400, and applied overhead of $2,890. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on credit) for $26,000, Job 121 is started and completed, and Job 122 is started and still in process at the end of July. Custom Cabinetry incurs the following costs during July. Job 120 Direct materials used Direct labor used $ 2,300 3,400 Job 121 $ 7,100 4,700 Job 122 $ 2,600 3,700 1. Prepare journal entries for the following July transactions and events a through e. a. Direct materials used. b. Direct labor used. c. Overhead applied. d. Sale of Job 120. e. Cost of goods sold for Job 120. Hint. Job 120 has costs from June and July. 2. Compute the July 31 balances of the Work in Process Inventory and the Finished Goods Inventory accounts. (There were no jobs in Finished Goods Inventory at June…arrow_forwardIn 2014, LL Bean sold 450,000 pairs of boots. At one point in 2014, it had a back order of 100,000. In 2015, LL Bean expects to sell 500,000 pairs of boots. As of late November 2015, it has a back order of 50,000.Question: When would LL Bean see sales revenue from the sale of its back order on the boots?arrow_forwardHelp me to solve this questionsarrow_forward
- correct answer pleasearrow_forwardGive this question financial accountingarrow_forward1.3 1.2.5 za When using a computerised accounting system, the paper work will be reduced in the organisation. Calculate the omitting figures: Enter only the answer next to the question number (1.3.1-1.3.5) in the NOTE. Round off to TWO decimals. VAT report of Comfy shoes as at 30 April 2021 OUTPUT TAX INPUT TAX NETT TAX Tax Gross Tax(15%) Gross (15%) Standard 75 614,04 1.3.1 Capital 1.3.2 9 893,36 94 924,94 Tax (15%) 1.3.3 Gross 484 782,70 75 849,08 -9 893,36 -75 849,08 Bad Debts TOTAL 1.3.4 4 400,00 1 922,27 14 737,42 -1 348,36 1.3.5 (5 x 2) (10arrow_forward
- Nonearrow_forwardWhat was her capital gains yield? General accountingarrow_forwardL.L. Bean operates two factories that produce its popular Bean boots (also known as "duck boots") in its home state of Maine. Since L.L. Bean prides itself on manufacturing its boots in Maine and not outsourcing, backorders for its boots can be high. In 2014, L.L. Bean sold about 450,000 pairs of the boots. At one point during 2014, it had a backorder level of about 100,000 pairs of boots. L.L. Bean can manufacture about 2,200 pairs of its duck boots each day with its factories running 24/7. In 2015, L.L. Bean expects to sell more than 500,000 pairs of its duck boots. As of late November 2015, the backorder quantity for Bean Boots was estimated to be about 50,000 pairs. Question:arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
![Text book image](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)