Concept explainers
1.
The direct materials cost variance, price variance and quantity variance.
1.

Explanation of Solution
Given,
The actual material used is 1,000,000 lbs.
The standard quantity of materials for actual production is 1,050,000 lbs.
The actual price is $4.25 per lb.
The standard price is $4.00 per lb.
Calculation of direct material cost variance:
Particulars | Amount ($) |
Actual units at actual cost | 4,250,000 |
Standard units at | 4,200,000 |
Direct material cost variance | 50,000 (unfavorable) |
The direct material cost variance is $50,000 (unfavorable).
Calculation of direct material price variance:
The formula to calculate the direct material price variance is,
Substitute 1,000,000 lb. for the actual quantity, $4.25 for the actual price and $4 for the standard price in the above formula.
The direct material price variance is $250,000 (unfavorable).
Calculation of direct material quantity variance:
The formula to calculate the direct material quantity variance is,
Substitute 1,000,000 lb for the actual quantity, 1,050,000 lb for standard quantity and $4.00 for standard price in the above formula.
The direct material quantity variance is $200,000 (unfavorable).
Hence, the direct material cost variance, price variance and quantity variance is $50,000 (unfavorable), $250,000 (unfavorable) and $200,000 (unfavorable).
2.
The direct labor cost, rate and efficiency variances.
2.

Explanation of Solution
Given,
The actual hours used is 250,000 hours.
The standard hours for actual production are 252,000 hours.
The actual rate is $7.75 per hour.
The standard rate is $8.00 per hour.
Calculation of direct labor cost variance:
Particulars | Amount ($) |
Actual hours at actual cost | 1,937,500 |
Standard hours at standard cost | 2,016,000 |
Direct labor cost variance | 78,500 (favorable) |
The direct labor cost variance is $78,500 (favorable).
Calculation of direct labor rate variance:
The formula to calculate the direct labor rate variance is,
Substitute 250,000 hours for the actual hours, $7.75 for the actual rate and $8 for the standard rate in the above formula.
The direct labor rate variance is $62,500 (favorable).
Calculation of direct labor efficiency variance:
The formula to calculate the direct labor efficiency variance is,
Substitute 250,000 for the actual hours, 252,000 for standard hours and $8.00 for standard rate in the above formula.
The direct labor efficiency variance is $16,000 (favorable).
Hence, the direct labor cost variance, rate variance and efficiency variance is $78,500 (favorable), $62,500 (favorable) and $16,000 (favorable).
3.
The
3.

Explanation of Solution
Calculation of the overhead controllable variance:
Particulars | Amount ($) |
Actual overhead incurred ($1,960,000+$1,200,000) | 3,160,000 |
Budgeted overhead (from flexible budget) | 3,276,000 |
Controllable overhead variance | 116,000 (favorable) |
The overhead controllable variance is $116,000 (favorable).
Calculation of the fixed overhead volume variance:
Particulars | Amount ($) |
Budgeted fixed overhead(at 80% capacity) | 2,016,000 |
Fixed overhead | 1,764,000 |
Fixed overhead volume variance | 252,000 (unfavorable) |
The fixed overhead volume variance is $252,000 (unfavorable).
Thus, the overhead controllable variance is $116,000 (favorable) and the fixed overhead volume variance is $252,000 (unfavorable).
Want to see more full solutions like this?
Chapter 8 Solutions
Managerial Accounting (Looseleaf)
- I am trying to find the accurate solution to this general accounting problem with appropriate explanations.arrow_forwardPlease provide the solution to this general accounting question with accurate financial calculations.arrow_forwardI need guidance with this general accounting problem using the right accounting principles.arrow_forward
- How can I solve this financial accounting problem using the appropriate financial process?arrow_forwardTransactions: Dec. 3 Wrote off Langston Corporation’s past-due account as uncollectible, $645.75. M203. 9 Accepted a 90-day, 8% note from Farris Company for an extension of time on its account, $2,400.00. NR23. 18 Received cash from Storage Solutions for the maturity value of NR19, a 90-day, 9% note for $2,000.00. R455. 21 Coastal Supply dishonored NR21, a 90-day, 8% note, for $3,000.00. M245. 30 Received cash in full payment of Langston Corporation’s account, previously written off as uncollectible, $645.75. M232 and R463. Task 1 Journalize the transactions for Miller Corporation in Questions Assets that were completed during December of the current year. Use page 12 of the general journal and page 12 of the cash receipts journal. Task 2 Post each entry to the general ledger and to the customer accounts in the accounts receivable ledger. You will not need to make entries to the Item columns of the ledgers. Task 3 Continue to…arrow_forwardE-M:11-18 Using payback to make capital investment decisions Consider the following three projects. All three have an initial investment of $600,000. Net Cash Inflows Year Project L Project M Project N Annual Accumulated Annual Accumulated Annual Accumulated 1 $ 150,000 $ 150,000 $ 100,000 $ 100,000 $ 300,000 $300,000 2 150,000 300,000 200,000 300,000 300,000 600,000 3 150,000 450,000 300,000 600,000 4 150,000 600,000 400,000 1,000,000 5 150,000 750,000 500,000 1,500,000 6 150,000 900,000 7 150,000 1,050,000 8 150,000 1,200,000 1. Determine the payback period of each project. Rank the projects from most desirable to least desirable based on payback. 2. Are there other factors that should be considered in addition to the payback period?arrow_forward
- Kindly help me with this General accounting questions not use chart gpt please fast given solutionarrow_forwardPlease help me solve this general accounting problem with the correct financial process.arrow_forwardCan you solve this general accounting problem using accurate calculation methods?arrow_forward
- Can you solve this general accounting problem using appropriate accounting principles?arrow_forwardHorngren's Financial & Managerial Accounting: The Managerial Chapters, 8th Edition E-M:10-12 Making pricing decisions Sufyan Builders builds 1,500-square-foot starter tract homes in the fast-growing suburbs of Atlanta. Competition among developers is fierce. The homes are a standard model, with any upgrades added by the buyer after the sale. Sufyan Builders’ costs per developed sublot are as follows:Land $ 59,000Construction 124,000Landscaping 6,000Variable selling costs 5,000 Sufyan Builders would like to earn a profit of 14% of the variable cost of each home sold. Similar homes offered by competing builders sell for $208,000 each. Assume the company has no fixed costs. Questions:1. Which approach to pricing should Sufyan Builders emphasize? Why? 2. Will Sufyan Builders be able to achieve its target profit levels? 3. Bathrooms and kitchens are typically the most important selling features of a home. Sufyan Builders could…arrow_forwardCan you provide a detailed solution to this financial accounting problem using proper principles?arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education