Question
Book Icon
Chapter 8, Problem 1RQ
To determine

The two stages involved in pricing of an estimate.

Expert Solution & Answer
Check Mark

Explanation of Solution

Pricing of estimate is defined as the process of approximately calculating the cost of the project after considering various factors influencing the cost of the project.

There are two stages of pricing of estimate and are given below.

Stage 1 − It is the starting phase and during this stage, a general list of all items required is prepared. This phase is also known as take off phase since take off of all items in the bid package is done.

Stage -2 − In this phase the price of all the items in the list is calculated. During this stage, the estimator focuses on one trade at a time while performing the pricing of items so it is considered as recap. This phase is known as recap. After finishing the recap, the summary of pricing for each craft is made. This makes the final bid easy.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
: For the gravity concrete dam shown in the figure, the following data are available: The factor of safety against sliding (F.S sliding)=1.2 Unit weight of concrete (Yconc)=24 KN/m³ - Neglect( Wave pressure, silt pressure, ice force and earth quake force) μ=0.65, (Ywater) = 9.81 KN/m³ Find factor of safety against overturning (F.S overturning) 6m3 80m Sm
Aum AA waste incinerator stack emits 27,027 kg/yr of cadmium and has an effective stack might of 100 m. The wind speed is 5 m/s at an anemometer located at 10 m. It is a clear sunny day with the sun nearly overhead (Class B conditions). a. Calculate the ground-level cadmium concentration (in ug/m³) at a distance of 2 km directly downwind? [Refer to tables in the textbook to help with this problem] What is the concentration of cadmium (in µg/m³) inside of a house at the location in part (a) after two hours? Note that the initial concentration of cadmium in the house was zero, there are 0.25 air changes per hour (ach), there is no source of cadmium inside the house, and cadmium is considered a conservative pollutant.
Must be handwrittenShow your complete solution with proper working equations.Express intermediate answers to at least four (4) decimal places and round final answers to two (2) decimal places. Enclose and summarize your final answers in a box

Chapter 8 Solutions

EBK FUNDAMENTALS OF CONSTRUCTION ESTIMA

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning